TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  12/11/2022 3:36:27PM Notice End Date/Time:  12/12/2022 9:00:00am
Post Date/Time:  12/11/2022 3:36:27 PM Notice ID: 385262
Reqrd Rsp:  1 Rsp Date:  12/11/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 12-11-2022 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of December 11, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 321 AND STA 245 FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

RESTRICTIONS

·         Whistle/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of SIPsp increases due to imbalance management quantity exceeded; 41,068 Dths

·         VCP/TGP Valley Crossing Allocation Receipt Meter (Pin 53608) - through 100% of SA increases due to operational concerns; 1,485 Dths

·         Enterprise/TGP Agua Dulce Nueces Receipt Meter (Pin 411306) - through 100% of SA increases due to operational concerns; 301 Dths

·         Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 32% of SOP increases due to operational concerns; 20,196 Dths

·         STA 834 (Segment 834 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 44,240 Dths

·         Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to nominations in excess of operational capacity; 10 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 74,334 Dths

·         STA 325 (Segment 324 FH) - through 100% of SIPsp increases due to force majeure between STA 325 to MLV 329; 104,781 Dths

·         Z5HC North (Segment 299 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 187,788 Dths

·         STA 245 (Segment 245 FH) - through 100% of SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity; 228,377 Dths

·         Wright Receipt Meter (Pin 412181) - through approx 55% of SIPss increases due to nominations in excess of operational capacity; 28,243 Dths

·         MLV 256 East (Segment 256 FH) - through approx 6% of SOP increases due to nominations in excess of operational capacity; 2,308 Dths

·         MLV 273 (Segment 284 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 37,125 Dths

LINEPACK RESTRICTIONS

Payback OFF the pipe will not be scheduled for all areas East of STA 321 and STA 245.  All payback in other areas will be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field. 

Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.