TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  12/08/2022 3:14:10PM Notice End Date/Time:  12/09/2022 9:00:00am
Post Date/Time:  12/8/2022 3:14:10 PM Notice ID: 385227
Reqrd Rsp:  1 Rsp Date:  12/08/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 12-08-2022 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of December 08, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

RESTRICTIONS

·         Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of SIPss increases  due to scheduled maintenance and nominations in excess of operational capacity; 2,959 Dths

·         Vcp/TGP Valley Crossing Allocation Receipt Meter (Pin 53608) - through 100% of SIPsp increases  due to scheduled maintenance and nominations in excess of operational capacity; 26,931 Dths

·         MLV 707 East - Carthage Lateral (Segment 700 FH) - through 100% of SA increases  due to nominations in excess of operational capacity; 9,245 Dths

·         Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 37% of SOP increases  due to operational concerns; 30,928 Dths

·         STA 834 (Segment 834 BH) - through approx 91% of SOP increases  due to nominations in excess of operational capacity; 72,956 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases  due to scheduled maintenance and emergent repair at STA 860; 7,816 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases  due to operational concerns; 10 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 35,791 Dths

·         STA 325 (Segment 324 FH) - through 100% of PIP increases  due to force majeure between STA 325 to MLV 329; 93,960 Dths

·         Z5HC North (Segment 299 FH) - through approx 75% of SOP increases  due to nominations in excess of operational capacity; 96,508 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 177,043 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 29,819 Dths

LINEPACK RESTRICTIONS

Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field. 

 

Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

 

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

....