Effective Intraday 2 Cycle (18:00) for the gas day of December 05, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of SA increases due to imbalance management quantity exceeded; 26,944 Dths
· Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SOP increases due to operational concerns; 39,948 Dths
· TGP/Php Sheridan Colorado Receipt Meter (Pin 54086) - through 100% of IT increases due to operational concerns; 5,188 Dths
· STA 834 (Segment 834 BH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 33,247 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and emergent repair at STA 860; 7,848 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to nominations in excess of operational capacity; 891 Dths
· Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through 100% of PAYBACK TGP increases due to nominations in excess of operational capacity; 3,570 Dths
· MLV 314 East (Segment 314 BH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 28,497 Dths
· STA 321 (Segment 321 FH) - through approx 72% of SOP increases due to nominations in excess of operational capacity; 122,977 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 29% of IT increases due to nominations in excess of operational capacity; 21,193 Dths
· MLV 336 East (Segment 336 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 28,819 Dths
· Z5HC North (Segment 299 FH) - through approx 59% of SOP increases due to nominations in excess of operational capacity; 61,269 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 110,743 Dths
· MLV 273 (Segment 284 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 27,790 Dths
LINEPACK RESTRICTIONS
Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.