Effective Evening Cycle (9:00) for the gas day of December 05, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SOP increases due to operational concerns; 49,348 Dths
· TGP/Php Sheridan Colorado Receipt Meter (Pin 54086) - through 100% of IT increases due to operational concerns; 5,188 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 18% of SOP increases due to imbalance management; 21,663 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and emergent repair at STA 860; 96,646 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 33% of SIPps increases due to nominations in excess of operational capacity; 19,993 Dths
· Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through 100% of PAYBACK TGP increases due to nominations in excess of operational capacity; 3,570 Dths
· MLV 314 East (Segment 314 BH) - through approx 35% of SOP increases due to nominations in excess of operational capacity; 31,408 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through approx 52% of IT increases due to nominations in excess of operational capacity; 8,991 Dths
· STA 321 (Segment 321 FH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 470,391 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 12% of SOP increases due to nominations in excess of operational capacity; 87,373 Dths
· MLV 336 East (Segment 336 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 28,819 Dths
· Z5HC North (Segment 299 FH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 167,939 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and emergent repair at STA 245 Unit 1C; 159,548 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 26% of SOP increases due to nominations in excess of operational capacity; 16,150 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 67,777 Dths
LINEPACK RESTRICTIONS
Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.