Effective Timely Cycle (9:00) for the gas day of December 03, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of IT due to imbalance management; 9,815 Dths
· Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SIPss due to operational concerns; 59,324 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 56% of SOP due to imbalance management; 186,472 Dths
· STA 834 (Segment 834 BH) - through approx 37% of SOP due to nominations in excess of operational capacity; 53,793 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and emergent repair at STA 860; 42,476 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 33% of SIPps due to nominations in excess of operational capacity; 98,455 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to force majeure at MLV 309 to MLV 310; 10,000 Dths
· MLV 314 East (Segment 314 BH) - through approx 47% of SOP due to nominations in excess of operational capacity; 93,642 Dths
· STA 315 (Segment 315 BH) - through approx 47% of SOP due to nominations in excess of operational capacity; 193,654 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through approx 8% of IT due to nominations in excess of operational capacity; 6,190 Dths
· STA 321 (Segment 321 FH) - through approx 74% of SOP due to nominations in excess of operational capacity; 723,528 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 76% of SOP due to nominations in excess of operational capacity; 274,360 Dths
· MLV 336 East (Segment 336 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 68,819 Dths
· Z5HC North (Segment 299 FH) - through approx 89% of SOP due to nominations in excess of operational capacity; 804,734 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP due to scheduled maintenance and emergent repair at STA 245 Unit 1C; 354,741 Dths
· Wright Receipt Meter (Pin 412181) - through approx 81% of SOP due to nominations in excess of operational capacity; 142,874 Dths
· MLV 273 (Segment 284 FH) - through approx 89% of SOP due to nominations in excess of operational capacity; 79,491 Dths
LINEPACK RESTRICTIONS
Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.