Effective Evening Cycle (9:00) for the gas day of December 02, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SIPss increases due to operational concerns; 12,387 Dths
· Trnsco/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through 100% of SOP increases due to operational concerns; 8,840 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 69% of SOP increases due to imbalance management; 139,714 Dths
· STA 834 (Segment 834 BH) - through approx 58% of SOP increases due to nominations in excess of operational capacity; 38,580 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance, nominations in excess of operational capacity and emergent repair at STA 860; 19,145 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· MLV 314 East (Segment 314 BH) - through approx 85% of SOP increases due to nominations in excess of operational capacity; 79,878 Dths
· STA 321 (Segment 321 FH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 527,718 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 59% of SOP increases due to nominations in excess of operational capacity; 203,855 Dths
· MLV 336 East (Segment 336 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 28,819 Dths
· STA 224 (Segment 224 FH) - through approx 56% of SOP increases due to nominations in excess of operational capacity; 8,638 Dths
· Z5HC North (Segment 299 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 211,670 Dths
· STA 245 (Segment 245 FH) - through 100% of PIP increases due to scheduled maintenance and emergent repair at STA 245 Unit 1C; 141,592 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 37% of SOP increases due to nominations in excess of operational capacity; 21,875 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 33,584 Dths
LINEPACK RESTRICTIONS
Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.