Effective Timely Cycle (9:00) for the gas day of November 23, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Atmos Tl/TGP Chauvin Ouachita Meter (Pin 47872) - through approx 12% of SOP due to exceeding family of contracts MDQ; 811 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 53% of SOP due to imbalance management; 163,262 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and emergent repair at STA 860; 51,773 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· Atmos Ky/TGP Lebanon Ky Marion Delivery Meter (Pin 420030) - through approx 3% of SOP due to nominations in excess of operational capacity; 250 Dths
· Atmos Ky/TGP Harrodsburg Ky Boyle Delivery Meter (Pin 420028) - through approx 12% of SIPss due to nominations in excess of operational capacity; 534 Dths
· Atmos Ky/TGP Danville Ky Boyle Delivery Meter (Pin 400462) - through approx 1% of SIPss due to nominations in excess of operational capacity; 29 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to force majeure at MLV 309 to MLV 310; 10,000 Dths
· MLV 314 East (Segment 314 BH) - through approx 58% of SOP due to nominations in excess of operational capacity; 126,089 Dths
· STA 315 (Segment 315 BH) - through approx 81% of SOP due to nominations in excess of operational capacity; 573,485 Dths
· STA 321 (Segment 321 FH) - through approx 89% of SOP due to nominations in excess of operational capacity; 749,557 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 48% of SIPss due to nominations in excess of operational capacity; 334,585 Dths
· MLV 336 East (Segment 336 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 28,819 Dths
· Z5HC North (Segment 299 FH) - through approx 96% of SOP due to nominations in excess of operational capacity; 815,461 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP due to scheduled maintenance and emergent repair at STA 245 Unit 1C; 389,005 Dths
· Wright Receipt Meter (Pin 412181) - through approx 60% of SIPss due to nominations in excess of operational capacity; 250,845 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 77% of SOP due to nominations in excess of operational capacity; 124,257 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 70,119 Dths
LINEPACK RESTRICTIONS
Payback to Tennessee will be evaluated at each cycle and scheduled if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.