Effective Intraday 1 Cycle (14:00) for the gas day of November 22, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 321 AND ALL AREAS EAST OF STA 245 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
RESTRICTIONS
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance, nominations in excess of operational capacity and emergent repair at STA 860; 71,106 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 79,839 Dths
· STA 321 (Segment 321 FH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 229,456 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 47% of SOP increases due to nominations in excess of operational capacity; 131,565 Dths
· MLV 336 East (Segment 336 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 28,819 Dths
· Z5HC North (Segment 299 FH) - through approx 87% of SOP increases due to nominations in excess of operational capacity; 203,518 Dths
· STA 245 (Segment 245 FH) - through 100% of PIP increases due to scheduled maintenance and emergent repair at STA 245 Unit 1C; 185,888 Dths
· Wright Receipt Meter (Pin 412181) - through approx 63% of SIPss increases due to nominations in excess of operational capacity; 209,783 Dths
· MLV 256 East (Segment 256 FH) - through approx 34% of SOP increases due to nominations in excess of operational capacity; 29,942 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 81,164 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 69,819 Dths
LINEPACK RESTRICTIONS
Payback to Tennessee will be evaluated at each cycle and scheduled if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.