Notice Detail
           
Return To Results
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  11/15/2022 11:05:45AM Notice End Date/Time:  11/16/2022 9:00:00am
Post Date/Time:  11/15/2022 11:05:45 AM Notice ID: 384974
Reqrd Rsp:  1 Rsp Date:  11/15/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 11-15-2022 ID1
Notice Text:

Effective Intraday 1 Cycle (14:00) for the gas day of November 15, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO BALANCING ALERT POINT SPECIFIC FOR 420926 FOR OVER-TAKES FROM THE SYSTEM and OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 321 ON THE 300 LEG ONLY FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM

RESTRICTIONS

·         Acadian/TGP Indian Bayou: Dip 510B- Delivery Meter (Pin 421056) - through 100% of SOP increases  due to pipeline maintenance at delivery location; 1,500 Dths

·         STA 823 (Segment 823 BH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 25,000 Dths

·         Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 99% of SOP increases  due to imbalance management quantity exceeded; 84,856 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases  due to operational concerns; 10 Dths

·         MLV 314 East (Segment 314 BH) - through approx 94% of SOP increases  due to nominations in excess of operational capacity; 50,697 Dths

·         STA 315 (Segment 315 BH) - through approx 74% of SOP increases  due to nominations in excess of operational capacity; 153,559 Dths

·         STA 321 (Segment 321 FH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 212,103 Dths

·         MLV 336 East (Segment 336 FH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 28,819 Dths

·         Z5HC North (Segment 299 FH) - through approx 95% of SOP increases  due to nominations in excess of operational capacity; 184,506 Dths

·         STA 245 (Segment 245 FH) - through approx 98% of SOP increases  due to emergent repair at STA 245 UNIT 1C; 378,544 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 23,606 Dths

LINEPACK RESTRICTIONS

Payback to Tennessee will be evaluated at each cycle and scheduled if operationally feasible. 

STORAGE RESTRICTIONS

Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field. 

Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

.