Effective Intraday 3 Cycle (22:00) for the gas day of November 04, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 0 (EXCLUDING AREAS SOUTH OF STA 1), L, 1, 2, 3, 4 AND 5 FOR OVER-DELIVERIES INTO THE SYSTEM OR UNDER-TAKES OUT OF THE SYSTEM FOR LMSMAs, SAs ACTING AS BALANCING PARTIES, AND LMSPAs and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· TGP/PHP Sheridan Colorado Receipt Meter (Pin 54086) - through 100% of SA increases due to operational concerns; 7,798 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 1,510 Dths
· Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 83% of SOP increases due to imbalance management quantity exceeded; 92,224 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 22,713 Dths
· TGP/SNG Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of SOP increases due to operational concerns; 6,785 Dths
· Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Pugh Mississippi Exch Lownd Delivery Meter (Pin 420294) - through approx 87% of SIPss increases due to operational concerns; 3,018 Dths
· STA 313 West (Segment 307 BH) - through 100% of IT increases due to force majeure at MLV 309 and MLV 310; 12,962 Dths
· MLV 314 East (Segment 314 BH) - through approx 79% of SOP increases due to nominations in excess of operational capacity; 68,303 Dths
· STA 315 (Segment 315 BH) - through approx 16% of SOP increases due to nominations in excess of operational capacity; 16,100 Dths
· Z5HC North (Segment 299 FH) - through approx 62% of SOP increases due to nominations in excess of operational capacity; 58,538 Dths
LINEPACK RESTRICTIONS
Payback to Tennessee will be evaluated at each cycle and scheduled if operationally feasible. Parks and Loan Paybacks utilizing the PALD and PALAO services under the PAL Rate Schedule will be scheduled until further notice.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.