Effective Intraday 2 Cycle (18:00) for the gas day of November 01, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 15% of SIPps increases due to imbalance management quantity exceeded; 100,915 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and emergent repair at STA 860; 84 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 99% of SIPps increases due to nominations in excess of operational capacity; 20,435 Dths
· TGP/SNG Pugh Mississippi Exch Lownd Delivery Meter (Pin 420294) - through approx 2% of SIPps increases due to nominations in excess of operational capacity; 507 Dths
· Atmos Ky/TGP Harrodsburg Ky Boyle Delivery Meter (Pin 420028) - through 100% of SIPss increases due to nominations in excess of operational capacity; 1,135 Dths
· STA 315 (Segment 315 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 218,270 Dths
· STA 325 (Segment 324 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 63,570 Dths
· Z5HC North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 194,845 Dths
· STA 245 (Segment 245 FH) - through approx 85% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 121,133 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 11,109 Dths
LINEPACK RESTRICTIONS
Payback to Tennessee will be evaluated at each cycle and scheduled if operationally feasible. Parks and Loan Paybacks utilizing the PALD and PALAO services under the PAL Rate Schedule will be scheduled until further notice.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.