Notice Detail
           
Return To Results
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  10/31/2022 7:48:51PM Notice End Date/Time:  11/01/2022 9:00:00am
Post Date/Time:  10/31/2022 7:48:51 PM Notice ID: 384815
Reqrd Rsp:  1 Rsp Date:  10/31/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 11-01-2022 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of November 01, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM

RESTRICTIONS

·         Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 70% of SOP increases  due to imbalance management quantity exceeded; 96,352 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases  due to scheduled maintenance and emergent repair at STA 860; 12,252 Dths

·         Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 77% of SIPss increases  due to imbalance management quantity exceeded; 8,589 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases  due to operational concerns; 19,740 Dths

·         TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 99% of SIPps increases  due to nominations in excess of operational capacity; 117,339 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 7,306 Dths

·         Atmos Ky/TGP Lebanon Ky Marion Delivery Meter (Pin 420030) - through approx 5% of SIPss increases  due to nominations in excess of operational capacity; 426 Dths

·         STA 110 South (Segment 187 BH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 78,425 Dths

·         STA 315 (Segment 315 BH) - through approx 99% of SOP increases  due to nominations in excess of operational capacity; 407,714 Dths

·         STA 321 (Segment 321 FH) - through approx 36% of SOP increases  due to nominations in excess of operational capacity; 162,452 Dths

·         STA 325 (Segment 324 FH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 178,413 Dths

·         Z5HC North (Segment 299 FH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 175,354 Dths

·         STA 245 (Segment 245 FH) - through approx 91% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 316,788 Dths

·         STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 36,015 Dths

·         Dynegy/TGP Blackstone Worchester Delivery Meter (Pin 420894) - through approx 79% of IT increases  due to nominations in excess of operational capacity; 11,816 Dths

·         MLV 273 (Segment 284 FH) - through approx 3% of SOP increases  due to nominations in excess of operational capacity; 633 Dths

LINEPACK RESTRICTIONS

Payback to Tennessee will be evaluated at each cycle and scheduled if operationally feasible.  Parks and Loan Paybacks utilizing the PALD and PALAO services under the PAL Rate Schedule will be scheduled until further notice.

STORAGE RESTRICTIONS

Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field. 

 

Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

 

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

..