Effective Intraday 1 Cycle (14:00) for the gas day of October 26, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· Tres Pal/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through approx 16% of IT increases due to imbalance management; 3,029 Dths
· Cproc/TGP Hcp Colorado Receipt Meter (Pin 410144) - through 100% of SOP increases due to operational concerns; 7,602 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 37,000 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 87% of SOP increases due to imbalance management; 121,385 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 17,444 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SOP increases due to operational concerns; 3,275 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP increases due to operational concerns; 9,531 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 66% of SOP increases due to nominations in excess of operational capacity; 3,291 Dths
· STA 114 East (Segment 114 BH) - through approx 99% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 54,784 Dths
· STA 204 (Segment 204 BH) - through approx 68% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 12,365 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 55,000 Dths
· MLV 314 East (Segment 314 BH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 112,380 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through approx 52% of IT increases due to nominations in excess of operational capacity; 1,719 Dths
· STA 321 (Segment 321 FH) - through approx 19% of SOP increases due to nominations in excess of operational capacity; 24,363 Dths
· Z5HC North (Segment 299 FH) - through approx 87% of SOP increases due to nominations in excess of operational capacity; 73,709 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 231,150 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 106,596 Dths
LINEPACK RESTRICTIONS
Payback to Tennessee will be evaluated at each cycle and scheduled if operationally feasible. Parks and Loan Paybacks utilizing the PALD and PALAO services under the PAL Rate Schedule will be scheduled until further notice.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.