TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  10/14/2022 3:34:45PM Notice End Date/Time:  10/15/2022 9:00:00am
Post Date/Time:  10/14/2022 3:34:45 PM Notice ID: 384632
Reqrd Rsp:  1 Rsp Date:  10/14/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 10-14-2022 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of October 14, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM

RESTRICTIONS

·         STA 823 (Segment 823 BH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 37,000 Dths

·         Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 75% of SOP increases  due to imbalance management; 104,779 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 36,738 Dths

·         Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 94% of SOP increases  due to imbalance management; 33,886 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases  due to operational concerns; 10 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases  due to force majeure at MLV 309 to MLV 310; 57,528 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 126,192 Dths

·         Z5HC North (Segment 299 FH) - through approx 42% of SOP increases  due to nominations in excess of operational capacity; 65,844 Dths

·         STA 261 Discharge East (Segment 261 FH) - through approx 5% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 3,502 Dths

·         MLV 273 (Segment 284 FH) - through approx 44% of SOP increases  due to nominations in excess of operational capacity; 17,401 Dths

LINEPACK RESTRICTIONS

No Payback TO the pipe will be scheduled Systemwide until further notice.  Payback system wide will continue to be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field. 

 

Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

No Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide until further notice.

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

.