Effective Intraday 1 Cycle (14:00) for the gas day of October 13, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· Tres Pal/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through approx 9% of IT increases due to imbalance management quantity exceeded; 1,240 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 37,000 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 82% of SOP increases due to imbalance management quantity exceeded; 100,094 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 19,957 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 2% of SIPps increases due to imbalance management quantity exceeded; 86 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 20% of SIPps increases due to nominations in excess of operational capacity; 1,079 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to operational concerns; 5,013 Dths
· STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 55,048 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 55,000 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 122,478 Dths
· Z5HC North (Segment 299 FH) - through approx 86% of SOP increases due to nominations in excess of operational capacity; 79,969 Dths
· STA 245 (Segment 245 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 171,184 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 110,255 Dths
LINEPACK RESTRICTIONS
No Payback TO the pipe will be scheduled Systemwide until further notice. Additionally, PALD and PALAO nominations ON system will not be scheduled. Payback system wide will continue to be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA). Transfers into TGP Bear Creek from SNG Bear Creek will be allowed only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.