Effective Timely Cycle (9:00) for the gas day of September 22, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through approx 31% of PIP due to scheduled maintenance and nominations in excess of operational capacity; 165,902 Dths
· STA 25 (Segment 125 BH) - through 100% of SA due to scheduled maintenance and nominations in excess of operational capacity; 46,735 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP due to operational concerns; 35,018 Dths
· Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 65% of SOP due to imbalance management quantity exceeded; 268,738 Dths
· Regency/TGP Peoples Road Franklin Receipt Meter (Pin 412691) - through 100% of SA due to operational concerns; 114,214 Dths
· ETC Tiger/TGP Ursus Franklin Receipt Meter (Pin 49589) - through 100% of SA due to operational concerns; 25,000 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 27,500 Dths
· TGP/SNG Toca Exchange St Bernard Delivery Meter (Pin 420556) - through approx 99% of SOP due to nominations in excess of operational capacity; 19,798 Dths
· Gulf South/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 42% of SIPps due to imbalance management quantity exceeded; 52,700 Dths
· Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 44% of SIPps due to nominations in excess of operational capacity; 221,008 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to operational concerns; 24,173 Dths
· STA 204 (Segment 204 BH) - through approx 96% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 115,733 Dths
· Hickory/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through approx 96% of PAYBACK TGP due to nominations in excess of operational capacity; 9,570 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to the force majeure at MLV 309 to MLV 310; 71,000 Dths
· STA 313 West (Segment 307 BH) - through 100% of SOP due to the force majeure at MLV 309 to MLV 310; 153,195 Dths
· MLV 314 East (Segment 314 BH) - through approx 99% of SOP due to nominations in excess of operational capacity; 171,969 Dths
· STA 315 (Segment 315 BH) - through approx 87% of SOP due to nominations in excess of operational capacity; 452,738 Dths
· STA 321 (Segment 321 FH) - through approx 81% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 691,299 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 44% of SOP due to nominations in excess of operational capacity; 52,023 Dths
· MLV 336 East (Segment 336 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 51,206 Dths
· STA 230B -Niagara Spur North (Segment 296 FH) - through approx 90% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 21,261 Dths
· Z5HC North (Segment 299 FH) - through approx 71% of SOP due to nominations in excess of operational capacity; 512,893 Dths
· STA 245 (Segment 245 FH) - through approx 65% of SOP due to nominations in excess of operational capacity; 445,018 Dths
· Wright Receipt Meter (Pin 412181) - through 100% of SIPss due to pipeline maintenance at receipt location; 100,668 Dths
· MLV 273 (Segment 284 FH) - through approx 95% of SOP due to nominations in excess of operational capacity; 258,706 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 in South Texas or on the 500 Line until further notice. PALD and PALAO nominations OFF the system will not be scheduled in these areas. Additionally, no Payback TO the pipe will be scheduled on the 800 Line until further notice. PALD and PALAO nominations TO the system on the 800 Leg will not be scheduled. Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.