Notice Detail
           
Return To Results
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  09/20/2022 3:30:05PM Notice End Date/Time:  09/21/2022 9:00:00am
Post Date/Time:  9/20/2022 3:30:05 PM Notice ID: 384363
Reqrd Rsp:  1 Rsp Date:  09/20/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  REVISED RESTRICTIONS FOR 09-21-2022 TC
Notice Text:

REVISED

Effective Timely Cycle (9:00) for the gas day of September 21, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM

RESTRICTIONS

·         MLV 406 (Segment 406 BH) - through approx 28% of PIP  due to scheduled maintenance and nominations in excess of operational capacity; 152,894 Dths

·         STA 823 (Segment 823 BH) - through 100% of SOP  due to operational concerns; 35,018 Dths

·         Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 47% of SOP  due to imbalance management quantity exceeded; 126,150 Dths

·         STA 834 (Segment 834 BH) - through approx 5% of SOP  due to nominations in excess of operational capacity; 6,688 Dths

·         Etc Tig/TGP Ursus Franklin Receipt Meter (Pin 49589) - through 100% of SA  due to nominations in excess of operational capacity; 54,530 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP  due to scheduled maintenance and nominations in excess of operational capacity; 118,877 Dths

·         TGP/SNG Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of SOP  due to nominations in excess of operational capacity;  19,846 Dths

·         Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 40% of SIPps  due to imbalance management quantity exceeded; 49,338 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps  due to operational concerns; 10 Dths

·         TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 43% of SIPps  due to nominations in excess of operational capacity; 225,455 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP  due to operational concerns; 39,799 Dths

·         Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through approx 96% of PAYBACK TGP  due to nominations in excess of operational capacity; 9,570 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP  due to force majeure at MLV 309 to MLV 310; 71,000 Dths

·         STA 313 West (Segment 307 BH) - through 100% of SOP  due to force majeure at MLV 309 to MLV 310; 160,769 Dths

·         MLV 314 East (Segment 314 BH) - through approx 73% of SOP  due to nominations in excess of operational capacity; 134,902 Dths

·         STA 315 (Segment 315 BH) - through approx 59% of SOP  due to nominations in excess of operational capacity; 238,495 Dths

·         STA 321 (Segment 321 FH) - through approx 53% of SOP  due to nominations in excess of operational capacity; 406,526 Dths

·         Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 3% of SIPss  due to nominations in excess of operational capacity; 146,044 Dths

·         MLV 336 East (Segment 336 FH) - through 100% of SOP  due to scheduled maintenance and nominations in excess of operational capacity; 50,250 Dths

·         STA 230B -Niagara Spur North (Segment 296 FH) - through 100% of SOP  due to scheduled maintenance and nominations in excess of operational capacity; 46,804 Dths

·         Z5HC North (Segment 299 FH) - through approx 70% of SOP  due to nominations in excess of operational capacity; 493,690 Dths

·         STA 245 (Segment 245 FH) - through approx 76% of SOP  due to nominations in excess of operational capacity; 522,715 Dths

·         Wright Receipt Meter (Pin 412181) - through 100% of SIPss  due to pipeline maintenance at receipt location; 117,821 Dths

·         STA 261 Discharge East (Segment 261 FH) - through approx 9% of SOP  due to scheduled maintenance and nominations in excess of operational capacity; 9,826 Dths

·         MLV 273 (Segment 284 FH) - through approx 97% of SOP  due to nominations in excess of operational capacity; 264,400 Dths

LINEPACK RESTRICTIONS

No Payback FROM the pipe will be scheduled South of STA 1 in South Texas or on the 500 Line until further notice.  PALD and PALAO nominations OFF the system will not be scheduled in these areas.  Additionally, no Payback TO the pipe will be scheduled on the 800 Line until further notice.  PALD and PALAO nominations TO the system on the 800 Leg will not be scheduled.  Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

NONE

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

...