Effective Evening Cycle (9:00) for the gas day of September 19, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through approx 94% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 112,106 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 35,018 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 66% of SOP increases due to imbalance management; 81,944 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 23,762 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPps increases due to imbalance management; 14,511 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 75% of SIPps increases due to nominations in excess of operational capacity; 31,016 Dths
· MLV 548 (Segment 542 BH) - through 100% of SA increases due to scheduled maintenance and nominations in excess of operational capacity; 10,000 Dths
· Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through 100% of PAYBACK TGP increases due to nominations in excess of operational capacity; 9,570 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310 55,000 Dths
· STA 313 West (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 113,231 Dths
· MLV 314 East (Segment 314 BH) - through approx 72% of SOP increases due to nominations in excess of operational capacity; 73,412 Dths
· STA 321 (Segment 321 FH) - through approx 72% of SOP increases due to nominations in excess of operational capacity; 252,333 Dths
· MLV 336 East (Segment 336 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 65,288 Dths
· Z5HC North (Segment 299 FH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 86,666 Dths
· STA 245 (Segment 245 FH) - through approx 19% of SOP increases due to nominations in excess of operational capacity; 18,856 Dths
· Wright Receipt Meter (Pin 412181) - through 100% of IT increases due to pipeline maintenance at receipt location; 7,380 Dths
· MLV 273 (Segment 284 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 174,971 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 in South Texas or on the 500 Line until further notice. PALD and PALAO nominations OFF the system will not be scheduled in these areas. Additionally, no Payback TO the pipe will be scheduled on the 800 Line until further notice. PALD and PALAO nominations TO the system on the 800 Leg will not be scheduled. Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.