Effective Intraday 3 Cycle (22:00) for the gas day of September 16, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· Net Mexi/TGP Gillrina Road Nueces Delivery Meter (Pin 47799) - through 100% of SOP Receipt increases due to operational concerns; 1,152 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 62% of SOP increases due to imbalance management; 80,189 Dths
· STA 834 (Segment 834 BH) - through approx 54% of SOP increases due to nominations in excess of operational capacity; 26,872 Dths
· Etc Tig/TGP Ursus Franklin Receipt Meter (Pin 49589) - through 100% of SA increases due to nominations in excess of operational capacity; 1,071 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP increases due to operational concerns; 1,352 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to nominations in excess of operational capacity; 4,436 Dths
· MLV 548 (Segment 542 BH) - through 100% of SA increases due to scheduled maintenance and nominations in excess of operational capacity; 10,000 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 6,098 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 in South Texas or on the 500 Line until further notice. PALD and PALAO nominations OFF the system will not be scheduled in these areas. Additionally, no Payback TO the pipe will be scheduled on the 800 Line until further notice. PALD and PALAO nominations TO the system on the 800 Leg will not be scheduled. Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.