Effective Evening Cycle (9:00) for the gas day of September 14, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through approx 88% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 112,638 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 37,017 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 73% of SOP increases due to imbalance management; 108,838 Dths
· STA 834 (Segment 834 BH) - through approx 37% of SOP increases due to nominations in excess of operational capacity; 21,685 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPps increases due to imbalance management; 4,582 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to nominations in excess of operational capacity; 85,502 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 21,866 Dths
· Atmos Ky/TGP Simpson Simpson Delivery Meter (Pin 421000) - through 100% of SIPss increases due to nominations in excess of operational capacity; 78 Dths
· Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through 100% of PAYBACK TGP increases due to nominations in excess of operational capacity; 9,570 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 55,000 Dths
· STA 313 West (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 100,791 Dths
· MLV 314 East (Segment 314 BH) - through approx 90% of SOP increases due to nominations in excess of operational capacity; 191,631 Dths
· STA 321 (Segment 321 FH) - through approx 84% of SOP increases due to nominations in excess of operational capacity; 241,490 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 64,799 Dths
· Z5HC North (Segment 299 FH) - through approx 81% of SOP increases due to nominations in excess of operational capacity; 105,055 Dths
· STA 245 (Segment 245 FH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 174,932 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 72% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 36,489 Dths
· MLV 273 (Segment 284 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 172,993 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 in South Texas or South of STA 542 on the 500 until further notice. PALD and PALAO nominations OFF the system will not be scheduled in these areas. Additionally, Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.