Notice Detail
           
Return To Results
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  09/03/2022 7:33:32PM Notice End Date/Time:  09/04/2022 9:00:00am
Post Date/Time:  9/3/2022 7:33:32 PM Notice ID: 384155
Reqrd Rsp:  1 Rsp Date:  09/03/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 09-03-2022 ID3
Notice Text:

Effective Intraday 3 Cycle (22:00) for the gas day of September 03, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM

RESTRICTIONS

·         STA 823 (Segment 823 BH) - through 100% of SOP increases  due to operational concerns; 2,017 Dths

·         Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 79% of SOP increases  due to imbalance management; 87,275 Dths

·         Gulfsth/TGP Kiln Miss Exchange Hanc Delivery Meter (Pin 420383) - through 100% of SOP increases  due to operational concerns; 5,000 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases  due to operational concerns; 10 Dths

·         Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP increases  due to operational concerns; 17,233 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SA increases  due to nominations in excess of operational capacity; 7,000 Dths

·         Atmos Ky/TGP Simpson Simpson Delivery Meter (Pin 421000) - through 100% of SIPss increases  due to nominations in excess of operational capacity; 114 Dths

LINEPACK RESTRICTIONS

No Payback FROM the pipe will be scheduled South of STA 1 in South Texas or South of STA 542 on the 500 until further notice.  PALD and PALAO nominations OFF the system will not be scheduled in these areas.  Additionally, Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

NONE

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

...