Effective Intraday 1 Cycle (14:00) for the gas day of September 02, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through approx 22% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,932 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 37,017 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 94% of SOP increases due to imbalance management; 95,164 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SOP increases due to operational concerns; 6,277 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP increases due to operational concerns; 4,657 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 99% of SIPps increases due to nominations in excess of operational capacity; 21,068 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 55,000 Dths
· STA 317 (Segment 317 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 43,106 Dths
· STA 321 (Segment 321 FH) - through approx 55% of SOP increases due to nominations in excess of operational capacity; 173,181 Dths
· STA 325 (Segment 324 FH) - through approx 96% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 72,740 Dths
· Z5HC North (Segment 299 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 109,679 Dths
· STA 245 (Segment 245 FH) - through approx 79% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 137,611 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 197,310 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 in South Texas or South of STA 542 on the 500 until further notice. PALD and PALAO nominations OFF the system will not be scheduled in these areas. Additionally, Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.