Notice Detail
           
Return To Results
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  08/15/2022 3:15:43PM Notice End Date/Time:  08/16/2022 9:00:00am
Post Date/Time:  8/15/2022 3:15:43 PM Notice ID: 383934
Reqrd Rsp:  1 Rsp Date:  08/15/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 08-15-2022 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of August 15, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM

RESTRICTIONS

·         STA 823 (Segment 823 BH) - through 100% of SOP increases  due to operational concerns; 6,976 Dths

·         STA 834 (Segment 834 BH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 74,841 Dths

·         Gulfsth/TGP Kiln Miss Exchange Hanc Delivery Meter (Pin 420383) - through 100% of SOP increases  due to operational concerns; 6,013 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases  due to operational concerns; 212 Dths

·         Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP increases  due to operational concerns; 17,233 Dths

·         TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases  due to nominations in excess of operational capacity; 8,067 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 33,243 Dths

·         Atmos Ky/TGP Harrodsburg Ky Boyle Delivery Meter (Pin 420028) - through 100% of SIPss increases  due to nominations in excess of operational capacity; 101 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases  due to force majeure at MLV 309 to MLV 310; 55,000 Dths

·         STA 313 West (Segment 307 BH) - through 100% of SOP increases  due to force majeure at MLV 309 to MLV 10; 36,414 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 118,485 Dths

·         STA 321 (Segment 321 FH) - through approx 69% of SOP increases  due to nominations in excess of operational capacity; 149,952 Dths

·         STA 237 West (Segment 233 FH) - through 100% of IT increases  due to scheduled maintenance and nominations in excess of operational capacity; 1,714 Dths

·         Z5HC North (Segment 299 FH) - through approx 74% of SOP increases  due to nominations in excess of operational capacity; 104,320 Dths

·         STA 245 (Segment 245 FH) - through approx 59% of SOP increases  due to nominations in excess of operational capacity; 86,545 Dths

·         MLV 273 (Segment 284 FH) - through approx 99% of SOP increases  due to nominations in excess of operational capacity; 45,411 Dths

LINEPACK RESTRICTIONS

No Payback FROM the pipe will be scheduled South of STA 1 in South Texas or South of STA 542 on the 500 until further notice.  PALD and PALAO nominations OFF the system will not be scheduled in these areas.  Additionally, Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

NONE

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

...