Effective Timely Cycle (9:00) for the gas day of August 08, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 245 ON THE 200 LINE FOR OVER-TAKES OUT OF THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through approx 35% of PIP due to scheduled maintenance and nominations in excess of operational capacity; 186,243 Dths
· Vcp/TGP Valley Crossing Allocation Receipt Meter (Pin 53608) - through 100% of IT due to operational concerns; 25,111 Dths
· Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SA due to operational concerns; 33,800 Dths
· Trnsco/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through 100% of SOP receipts due to displacement gas unavailable for backhaul; 30,000 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 37,063 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 38% of SOP due to imbalance management; 102,983 Dths
· STA 834 (Segment 834 BH) - through approx 12% of SOP due to nominations in excess of operational capacity; 18,805 Dths
· STA 860 (Segment 860 BH) - through approx 53% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 49,638 Dths
· Fgt/TGP Carnes Mississippi Stone Delivery Meter (Pin 420366) - through 100% of SOP due to operational concerns; 8,000 Dths
· TGP/Sng Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of SOP due to nominations in excess of operational capacity; 19,846 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP due to operational concerns; 19,730 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SOP due to operational concerns; 12,000 Dths
· Sesh/TGP Petal Interconnect: Rip 53 Delivery Meter (Pin 421059) - through 100% of SOP due to operational concerns; 64 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 41% of SIPps due to nominations in excess of operational capacity; 193,991 Dths
· TGP/Sng Pugh Mississippi Exch Lownd Delivery Meter (Pin 420294) - through 100% of SOP receipts due to displacement gas unavailable for backhaul; 5,200 Dths
· STA 860 South 500 Line (Segment 548 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 55,000 Dths
· STA 204 (Segment 204 BH) - through approx 15% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 18,608 Dths
· Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through approx 96% of PAYBACK TGP due to nominations in excess of operational capacity; 9,570 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to force majeure at MLV 309 to MLV 310; 305,514 Dths
· MLV 314 East (Segment 314 BH) - through approx 89% of SOP due to nominations in excess of operational capacity; 118,234 Dths
· STA 315 (Segment 315 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 389,665 Dths
· STA 321 (Segment 321 FH) - through approx 59% of SOP due to nominations in excess of operational capacity; 491,229 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 16% of SIPss due to nominations in excess of operational capacity; 103,678 Dths
· STA 224 (Segment 224 BH) - through approx 33% of SOP due to nominations in excess of operational capacity; 93,378 Dths
· Z5HC North (Segment 299 FH) - through approx 75% of SOP due to nominations in excess of operational capacity; 570,149 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 735,829 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 149,028 Dths
· MLV 273 (Segment 284 FH) - through approx 99% of SOP due to nominations in excess of operational capacity; 204,000 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 in South Texas, South of STA 542 on the 500 Leg or East of STA 245 on the 200 Line until further notice. PALD and PALAO nominations OFF the system will not be scheduled in these areas. Additionally, Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.