Effective Evening Cycle (9:00) for the gas day of August 04, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 245 ON THE 200 LINE FOR OVER-TAKES OUT OF THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through approx 99% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 47,703 Dths
· Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of SOP increases due to operational concerns; 15,172 Dths
· Vcp/TGP Valley Crossing Allocation Receipt Meter (Pin 53608) - through 100% of SOP increases due to operational concerns; 73,111 Dths
· Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SOP increases due to operational concerns; 7,000 Dths
· Etp/TGP Shoup Nueces Receipt Meter (Pin 412669) - through 100% of SOP increases due to operational concerns; 300 Dths
· Cproc/TGP Hcp Colorado Receipt Meter (Pin 410144) - through 100% of SOP increases due to operational concerns; 15,753 Dths
· TGP/Php Sheridan Colorado Receipt Meter (Pin 54086) - through 100% of SOP increases due to operational concerns; 1,656 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 37,039 Dths
· STA 860 (Segment 860 BH) - through approx 76% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 99,500 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to nominations in excess of operational capacity; 38,879 Dths
· Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through 100% of PAYBACK TGP increases due to nominations in excess of operational capacity; 9,570 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 55,000 Dths
· STA 313 West (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 141,205 Dths
· MLV 314 East (Segment 314 BH) - through approx 84% of SOP increases due to nominations in excess of operational capacity; 82,262 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through approx 4% of SOP increases due to nominations in excess of operational capacity; 11,539 Dths
· STA 321 (Segment 321 FH) - through approx 87% of SOP increases due to nominations in excess of operational capacity; 265,275 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 64,734 Dths
· Z5HC North (Segment 299 FH) - through approx 53% of SOP increases due to nominations in excess of operational capacity; 58,019 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 258,331 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 82,764 Dths
· Mill Pow/TGP Millennium Power Cogen Delivery Meter (Pin 420884) - through approx 25% of SOP increases due to nominations in excess of operational capacity; 4,831 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 116,089 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 in South Texas, South of STA 542 on the 500 Leg or East of STA 245 on the 200 Line until further notice. PALD and PALAO nominations OFF the system will not be scheduled in these areas. Additionally, Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.