Effective Intraday 2 Cycle (18:00) for the gas day of August 03, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,275 Dths
· Cproc/TGP Hcp Colorado Receipt Meter (Pin 410144) - through 100% of SOP increases due to operational concerns; 4,694 Dths
· TGP/Php Sheridan Colorado Receipt Meter (Pin 54086) - through 100% of SOP increases due to operational concerns; 4,623 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 37,017 Dths
· STA 860 (Segment 860 BH) - through approx 69% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 66,017 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPps increases at the group level (Delivery meters South of STA 542) due to operational concerns; 1,981 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps increases at the group level (Delivery meters South of STA 542) due to operational concerns; 17,124 Dths
· TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to nominations in excess of operational capacity; 858 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV309 to MLV 310; 91,414 Dths
· MLV 314 East (Segment 314 BH) - through approx 52% of SOP increases due to nominations in excess of operational capacity; 16,106 Dths
· STA 230B -Niagara Spur North (Segment 296 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 15,000 Dths
· Z5HC North (Segment 299 FH) - through approx 76% of SOP increases due to nominations in excess of operational capacity; 99,067 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 165,786 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 40,435 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 until further notice. Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.