Effective Intraday 2 Cycle (18:00) for the gas day of August 02, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,229 Dths
· Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SA increases due to operational concerns; 7,000 Dths
· Cproc/TGP Hcp Colorado Receipt Meter (Pin 410144) - through 100% of SOP increases due to operational concerns; 5,674 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 37,017 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 126,850 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases at the group level (Delivery meters South of STA 542) due to operational concerns; 10 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps increases at the group level (Delivery meters South of STA 542) due to operational concerns; 20,431 Dths
· TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases at the group level (Delivery meters South of STA 542) due to operational concerns; 596 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 91,414 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 31,101 Dths
· STA 321 (Segment 321 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 275,135 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 5% of SOP increases due to nominations in excess of operational capacity; 3,125 Dths
· STA 230B -Niagara Spur North (Segment 296 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 15,000 Dths
· Z5HC North (Segment 299 FH) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 84,217 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 227,524 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 45,089 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 until further notice. Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.