Effective Timely Cycle (9:00) for the gas day of August 02, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through approx 41% of PIP due to scheduled maintenance and nominations in excess of operational capacity; 165,918 Dths
· Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SOP due to operational concerns; 50,277 Dths
· Cccpl/TGP Sinton San Patricio Receipt Meter (Pin 49861) - through approx 25% of SOP due to operational concerns; 13,216 Dths
· Vcp/TGP Valley Crossing Allocation Receipt Meter (Pin 53608) - through 100% of SOP due to operational concerns; 73,111 Dths
· Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of SOP due to operational concerns; 29,877 Dths
· Banhub/TGP Banquete Transport Nuece Receipt Meter (Pin 412062) - through 100% of SOP due to operational concerns; 20,011 Dths
· TGP/Php Sheridan Colorado Receipt Meter (Pin 54086) - through approx 27% of SOP due to operational concerns; 9,245 Dths
· Cpn/TGP Hcp Colorado Receipt Meter (Pin 410144) - through approx 56% of SOP due to operational concerns; 11,165 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP due to operational concerns; 37,063 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 226,609 Dths
· Gulfsth/TGP Kiln Miss Exchange Hanc Delivery Meter (Pin 420383) - through approx 25% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 9,335 Dths
· TGP/Sng Toca Exchange St Bernard Delivery Meter (Pin 420556) - through approx 25% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 83,108 Dths
· TGP/Sng Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of SOP receipts due to displacement gas unavailable for backhaul; 178,555 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through approx 25% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 45,603 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 25% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 37,132 Dths
· Sesh/TGP Petal Interconnect: Rip 53 Delivery Meter (Pin 421059) - through approx 25% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 68,290 Dths
· TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 25% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 165,480 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SA receipts due to displacement gas unavailable for backhaul; 3,454 Dths
· MLV 548 (Segment 542 BH) - through approx 31% of SA due to nominations in excess of operational capacity; 8,261 Dths
· STA 860 South 500 Line (Segment 548 BH) - through 100% of SOP due to nominations in excess of operational capacity; 20,026 Dths
· Atmos Ky/TGP Danville Ky Boyle Delivery Meter (Pin 400462) - through approx 65% of SIPss due to nominations in excess of operational capacity; 478 Dths
· STA 204 (Segment 204 BH) - through approx 47% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 57,057 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to force majeure at MLV 309 to MLV 310; 71,000 Dths
· STA 313 West (Segment 307 BH) - through 100% of SOP due to force majeure at MLV 309 to MLV 310; 236,824 Dths
· MLV 314 East (Segment 314 BH) - through approx 96% of SOP due to nominations in excess of operational capacity; 159,559 Dths
· STA 315 (Segment 315 BH) - through approx 68% of SOP due to nominations in excess of operational capacity; 261,319 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through approx 10% of SOP due to nominations in excess of operational capacity; 32,061 Dths
· STA 321 (Segment 321 FH) - through approx 57% of SOP due to nominations in excess of operational capacity; 437,263 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 4% of SIPss due to nominations in excess of operational capacity; 94,349 Dths
· STA 230B -Niagara Spur North (Segment 296 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 49,931 Dths
· Z5HC North (Segment 299 FH) - through approx 72% of SOP due to nominations in excess of operational capacity; 551,650 Dths
· STA 245 (Segment 245 FH) - through approx 83% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 544,854 Dths
· MLV 273 (Segment 284 FH) - through approx 99% of SOP due to nominations in excess of operational capacity; 220,082 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 until further notice. Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.