Effective Intraday 1 Cycle (14:00) for the gas day of July 29, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS ON THE 500 LEG BETWEEN STA 860 AND STA 527 FOR LMS-PA, SA ACTING AS BALANCING PARTIES AND LMS-MA FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM
OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 721 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 36,960 Dths
· STA 834 (Segment 834 BH) - through approx 43% of SOP increases due to nominations in excess of operational capacity; 74,325 Dths
· Gulf South/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 8,152 Dths
· Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 110 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 7,819 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 1,149 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 55,000 Dths
· STA 313 West (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 36,414 Dths
· MLV 314 East (Segment 314 BH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 104,602 Dths
· STA 321 (Segment 321 FH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 199,765 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 49% of SOP increases due to nominations in excess of operational capacity; 21,645 Dths
· Z5HC North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 20,019 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 131,768 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 179,148 Dths
LINEPACK RESTRICTIONS
No Loans or Park Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services on the 500 Leg between STA 860 and STA 527 until further notice. No Payback FROM the pipe greater than the supply tolerance (100 Dths) will be allowed in on the 500 Leg between STA 860 and STA 527 until further notice. Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.