TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  07/21/2022 2:28:34PM Notice End Date/Time:  07/22/2022 9:00:00am
Post Date/Time:  7/21/2022 2:28:34 PM Notice ID: 383655
Reqrd Rsp:  1 Rsp Date:  07/21/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 07-22-2022 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of July 22, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES L, 1 AND 2 FOR LMS-PA, SA ACTING AS BALANCING PARTIES AND LMS-MA FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM and OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM

RESTRICTIONS

·         MLV 406 (Segment 406 BH) - through approx 38% of PIP due to scheduled maintenance and nominations in excess of operational capacity; 243,864 Dths

·         STA 823 (Segment 823 BH) - through 100% of SOP due to operational concerns; 25,774 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 208,506 Dths

·         Fgt/TGP Carnes Mississippi Stone Delivery Meter (Pin 420366) - through approx 26% of SIPps at the group level (Delivery meters South of STA 542) due to operational concerns; 565 Dths

·         Gulfsth/TGP Kiln Miss Exchange Hanc Delivery Meter (Pin 420383) - through approx 26% of SIPps  at the group level (Delivery meters South of STA 542) due to operational concerns; 8,586 Dths

·         Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through approx 26% of SIPps  at the group level (Delivery meters South of STA 542) due to operational concerns; 59,804 Dths

·         TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 26% of SIPps  at the group level (Delivery meters South of STA 542) due to operational concerns; 165,820 Dths

·         Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 26% of SIPps  at the group level (Delivery meters South of STA 542) due to operational concerns; 28,521 Dths

·         Sesh/TGP Petal Interconnect: Rip 53 Delivery Meter (Pin 421059) - through approx 26% of SIPps  at the group level (Delivery meters South of STA 542) due to operational concerns; 55,272 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps  due to operational concerns; 110 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 23,591 Dths

·         STA 860 South 500 Line (Segment 548 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 5,034 Dths

·         STA 110 South (Segment 187 BH) - through 100% of IT due to scheduled maintenance and nominations in excess of operational capacity; 41,377 Dths

·         Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through approx 96% of PAYBACK TGP due to nominations in excess of operational capacity; 9,570 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP  due to force majeure at MLV 309 to MLV 310; 313,834 Dths

·         MLV 314 East (Segment 314 BH) - through approx 84% of SOP  due to nominations in excess of operational capacity; 104,950 Dths

·         STA 315 (Segment 315 BH) - through approx 60% of SOP  due to nominations in excess of operational capacity; 176,341 Dths

·         STA 321 (Segment 321 FH) - through approx 59% of SOP  due to nominations in excess of operational capacity; 490,850 Dths

·         Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 50% of SIPss  due to nominations in excess of operational capacity; 106,503 Dths

·         MLV 355 (Segment 355 BH) - through 100% of SOP  due to operational concerns; 10,555 Dths

·         Z5HC North (Segment 299 FH) - through approx 74% of SOP  due to nominations in excess of operational capacity; 537,628 Dths

·         STA 245 (Segment 245 FH) - through approx 85% of SOP  due to nominations in excess of operational capacity; 496,399 Dths

·         STA 261 Discharge East (Segment 261 FH) - through 100% of SOP  due to scheduled maintenance and nominations in excess of operational capacity; 261,423 Dths

·         MLV 273 (Segment 284 FH) - through approx 71% of SOP  due to nominations in excess of operational capacity; 138,266 Dths

LINEPACK RESTRICTIONS

No Loans or Park Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services in Zones L, 1 and 2 further notice. No Payback FROM the pipe greater than the supply tolerance (100 Dths) will be allowed in Zones L, 1 and 2 until further notice.  Payback systemwide will be evaluated at each cycle and scheduled only if operationally feasible. 

STORAGE RESTRICTIONS

NONE

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

.