TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  07/18/2022 3:44:56PM Notice End Date/Time:  07/19/2022 9:00:00am
Post Date/Time:  7/18/2022 3:44:56 PM Notice ID: 383626
Reqrd Rsp:  1 Rsp Date:  07/18/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 07-18-2022 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of July 18, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES L, 1 AND 2 FOR LMS-PA, SA ACTING AS BALANING PARTIES AND LMS-MA FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM and OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM

RESTRICTIONS

·         MLV 406 (Segment 406 BH) - through 100% of PIP increases  due to scheduled maintenance and nominations in excess of operational capacity; 542 Dths

·         STA 823 (Segment 823 BH) - through 100% of SOP increases  due to operational concerns; 36,994 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 158,472 Dths

·         Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPps increases  due to operational concerns; 3,194 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases  due to operational concerns; 110 Dths

·         Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps increases  due to operational concerns; 8,931 Dths

·         TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases  due to operational concerns; 6,998 Dths

·         STA 110 South (Segment 187 BH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 5,018 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases  due to force majeure at MLV  309 to MLV 310; 91,414 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 27,341 Dths

·         Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 94% of SOP increases  due to nominations in excess of operational capacity; 89,040 Dths

·         Z5HC North (Segment 299 FH) - through approx 99% of SOP increases  due to nominations in excess of operational capacity; 125,747 Dths

·         STA 245 (Segment 245 FH) - through approx 93% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 167,467 Dths

LINEPACK RESTRICTIONS

No Loans or Park Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services in Zones L, 1 and 2 further notice. No Payback FROM the pipe greater than the supply tolerance (100 Dths) will be allowed in Zones L, 1 and 2 until further notice.  Payback systemwide will be evaluated at each cycle and scheduled only if operationally feasible. 

STORAGE RESTRICTIONS

NONE

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

....