Effective Intraday 2 Cycle (18:00) for the gas day of July 17, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONE L AND ZONE 1 FOR THE 500 LEG ONLY BETWEEN STA 860 AND STA 534 FOR LMS-PA, SA ACTING AS BALANING PARTIES AND LMS-MA FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM and OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 406 (Segment 406 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,056 Dths
· STA 834 (Segment 834 BH) - through approx 63% of SOP increases due to nominations in excess of operational capacity; 76,375 Dths
· STA 860 (Segment 860 BH) - through approx 77% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 34,807 Dths
· TGP/Sng Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of SIPps increases due to operational concerns; 177 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPps increases due to operational concerns; 478 Dths
· Sesh/TGP Petal Interconnect: Rip 53 Delivery Meter (Pin 421059) - through 100% of SIPps increases due to operational concerns; 5,061 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 110 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps increases due to operational concerns; 6,748 Dths
· TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to operational concerns; 3,475 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 15,000 Dths
· Atmos Ky/TGP Harrodsburg Ky Boyle Delivery Meter (Pin 420028) - through 100% of SIPss increases due to nominations in excess of operational capacity; 3 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 and MLV 310; 91,414 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 22,792 Dths
· STA 315 (Segment 315 BH) - through approx 21% of SOP increases due to nominations in excess of operational capacity; 6,182 Dths
· Z5HC North (Segment 299 FH) - through approx 67% of SOP increases due to nominations in excess of operational capacity; 66,064 Dths
· STA 245 (Segment 245 FH) - through approx 47% of SOP increases due to nominations in excess of operational capacity; 70,175 Dths
· MLV 273 (Segment 284 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 38,798 Dths
LINEPACK RESTRICTIONS
No Loans or Park Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services on the 500 Leg until further notice. No Payback FROM the pipe greater than the supply tolerance (100 Dths) will be allowed on the 500 Leg until further notice. Additionally, Payback FROM the pipe South of STA 1 will not be scheduled until further notice. Payback systemwide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.