Notice Detail
           
Return To Results
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  07/16/2022 7:46:32PM Notice End Date/Time:  07/17/2022 9:00:00am
Post Date/Time:  7/16/2022 7:46:32 PM Notice ID: 383608
Reqrd Rsp:  1 Rsp Date:  07/16/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 07-17-2022 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of July 17, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONE L AND ZONE 1 FOR THE 500 LEG ONLY BETWEEN STA 860 AND STA 534 FOR LMS-PA, SA ACTING AS BALANING PARTIES AND LMS-MA FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM and OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM

RESTRICTIONS

·         MLV 406 (Segment 406 BH) - through approx 87% of PIP increases  due to scheduled maintenance and nominations in excess of operational capacity; 131,625 Dths

·         STA 834 (Segment 834 BH) - through approx 45% of SOP increases  due to nominations in excess of operational capacity; 100,155 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases  due to scheduled maintenance and nominations in excess of operational capacity; 105,360 Dths

·         Gulfsth/TGP Kiln Miss Exchange Hanc Delivery Meter (Pin 420383) - through 100% of SIPps increases  due to operational concerns; 22,599 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases  due to operational concerns; 110 Dths

·         Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps increases  due to operational concerns; 4,999 Dths

·         TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases  due to operational concerns; 3,475 Dths

·         Atmos Ky/TGP Harrodsburg Ky Boyle Delivery Meter (Pin 420028) - through 100% of SIPss increases  due to nominations in excess of operational capacity; 253 Dths

·         Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through 100% of PAYBACK TGP increases  due to nominations in excess of operational capacity; 9,570 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases  due to force majeure at MLV 309 and MLV 310; 185,774 Dths

·         MLV 314 East (Segment 314 BH) - through approx 97% of SOP increases  due to nominations in excess of operational capacity; 31,455 Dths

·         STA 315 (Segment 315 BH) - through approx 68% of SOP increases  due to nominations in excess of operational capacity; 75,094 Dths

·         STA 321 (Segment 321 FH) - through approx 76% of SOP increases  due to nominations in excess of operational capacity; 150,334 Dths

·         Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 91% of SOP increases  due to nominations in excess of operational capacity; 175,842 Dths

·         Z5HC North (Segment 299 FH) - through approx 66% of SOP increases  due to nominations in excess of operational capacity; 62,693 Dths

·         STA 245 (Segment 245 FH) - through approx 78% of SOP increases  due to nominations in excess of operational capacity; 149,173 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 180,821 Dths

LINEPACK RESTRICTIONS

No Loans or Park Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services on the 500 Leg until further notice. No Payback FROM the pipe greater than the supply tolerance (100 Dths) will be allowed on the 500 Leg until further notice.  Additionally, Payback FROM the pipe South of STA 1 will not be scheduled until further notice.  Payback systemwide will be evaluated at each cycle and scheduled only if operationally feasible. 

STORAGE RESTRICTIONS

NONE

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

..