Effective Intraday 3 Cycle (22:00) for the gas day of July 15, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONE L AND ZONE 1 FOR THE 500 LEG ONLY BETWEEN STA 860 AND STA 534 FOR LMS-PA, SA ACTING AS BALANING PARTIES AND LMS-MA FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM and OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 160,940 Dths
· Gulfsth/TGP Kiln Miss Exchange Hanc Delivery Meter (Pin 420383) - through 100% of SIPps increases due to operational concerns; 5,725 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPps increases due to operational concerns; 11,341 Dths
· Sesh/TGP Petal Interconnect: Rip 53 Delivery Meter (Pin 421059) - through 100% of SIPps increases due to operational concerns; 2,856 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 110 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SIPps increases due to operational concerns; 1,984 Dths
· TGP/Sng Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to operational concerns; 2,713 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 4,915 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 and MLV 310; 36,414 Dths
LINEPACK RESTRICTIONS
No Loans or Park Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services on the 500 Leg until further notice. No Payback FROM the pipe greater than the supply tolerance (100 Dths) will be allowed on the 500 Leg until further notice. Additionally, Payback FROM the pipe South of STA 1 will not be scheduled until further notice. Payback systemwide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.