Effective Intraday 3 Cycle (22:00) for the gas day of July 08, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONE L AND ZONE 1 FOR THE 500 LEG ONLY BETWEEN STA 860 AND STA 534 FOR LMS-PA, SA ACTING AS BALANING PARTIES AND LMS-MA FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM and MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 1,989 Dths
· STA 834 (Segment 834 BH) - through approx 44% of SOP increases due to nominations in excess of operational capacity; 38,726 Dths
· TGP/Sng Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of SOP increases due to operational concerns; 5,438 Dths
· Fgt/TGP Carnes Mississippi Stone Delivery Meter (Pin 420366) - through 100% of SOP increases due to operational concerns; 88 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 110 Dths
· STA 860 South 500 Line (Segment 548 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 35,524 Dths
LINEPACK RESTRICTIONS
No Loans or Park Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services on the 500 Leg until further notice. No Payback FROM the pipe greater than the supply tolerance (100 Dths) will be allowed on the 500 Leg until further notice. Payback systemwide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.