Effective Timely Cycle (9:00) for the gas day of July 03, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· STA 823 (Segment 823 BH) - through approx 68% of SOP due to nominations in excess of operational capacity; 165,916 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 241,122 Dths
· Greenbrier TN 2 (Dual) Receipt Meter (Pin 420289) - through 100% of SIPss receipts due to displacement gas unavailable for backhaul; 537 Dths
· Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 31,645 Dths
· Atmos KY/TGP Simpson Simpson Delivery Meter (Pin 421000) - through approx 15% of SIPss due to nominations in excess of operational capacity; 70 Dths
· STA 307 (Segment 307 BH) - through approx 69% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 214,818 Dths
· MLV 314 East (Segment 314 BH) - through approx 95% of SOP due to nominations in excess of operational capacity; 135,989 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP due to nominations in excess of operational capacity; 303,101 Dths
· STA 321 (Segment 321 FH) - through approx 51% of SOP due to nominations in excess of operational capacity; 368,828 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 4% of SIPss due to nominations in excess of operational capacity; 187,765 Dths
· MLV 355 (Segment 355 BH) - through 100% of SOP due to operational concerns; 2,613 Dths
· Z5HC North (Segment 299 FH) - through approx 67% of SOP due to nominations in excess of operational capacity; 465,474 Dths
· STA 245 (Segment 245 FH) - through approx 63% of SOP due to nominations in excess of operational capacity; 421,902 Dths
· MLV 273 (Segment 284 FH) - through approx 98% of SOP due to nominations in excess of operational capacity; 288,365 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.