TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  09/10/2021 2:37:31PM Notice End Date/Time:  10/10/2021 9:00:00am
Post Date/Time:  9/10/2021 2:37:31 PM Notice ID: 380237
Reqrd Rsp:  1 Rsp Date:  09/10/2021
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 09-11-2021 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of September 11, 2021 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ALL AREAS SOUTH OF STA 9 FOR OVER-TAKES OUT OF THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and OFO MONTHLY CRITICAL DAY 1 FOR ALL OF ZONE 4 FOR OVER-DELIVERIES INTO THE SYSTEM FOR LMPA AND SA BALANCING PARTIES

RESTRICTIONS

·         STA 1 (Segment 101 BH) - through 100% of SOP  due to nominations in excess of operational capacity; 29,303 Dths

·         STA 834 (Segment 834 BH) - through approx 56% of SOP  due to nominations in excess of operational capacity; 116,122 Dths

·         STA 114 East (Segment 114 BH) - through approx 37% of SIPps  due to scheduled maintenance and nominations in excess of operational capacity; 101,553 Dths

·         MLV 217 (Segment 217 BH) - through 100% of SOP  due to operational concerns; 2,299 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP  due to scheduled maintenance and nominations in excess of operational capacity; 14,705 Dths

·         MLV 314 East (Segment 314 BH) - through approx 99% of SOP  due to nominations in excess of operational capacity; 117,518 Dths

·         STA 315 (Segment 315 BH) - through approx 84% of SOP  due to nominations in excess of operational capacity; 239,576 Dths

·         STA 321 (Segment 321 FH) - through approx 34% of SOP  due to nominations in excess of operational capacity; 257,457 Dths

·         Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 34% of SIPss  due to nominations in excess of operational capacity; 120,033 Dths

·         MLV 355 (Segment 355 BH) - through 100% of SOP  due to operational concerns; 989 Dths

·         MLV 230 (Segment 230 BH) - through 100% of SOP  due to force majeure; 6,513 Dths

·         STA 237 West (Segment 233 FH) - through 100% of IT  due to force majeure; 80,769 Dths

·         Z5HC North (Segment 299 FH) - through approx 57% of SOP  due to nominations in excess of operational capacity; 386,275 Dths

·         STA 245 (Segment 245 FH) - through approx 58% of SOP  due to nominations in excess of operational capacity; 351,792 Dths

·         Mill Pow/TGP Millennium Power Cogen Delivery Meter (Pin 420884) - through approx 12% of SOP  due to nominations in excess of operational capacity; 18,330 Dths

·         MLV 273 (Segment 284 FH) - through approx 87% of SOP  due to nominations in excess of operational capacity; 240,017 Dths

LINEPACK RESTRICTIONS

Payback nominations FROM the pipe in all areas South of STA 9 as well as Payback nominations TO the pipe in Zone 4 will be evaluated at each cycle and scheduled only if operationally feasible. 

STORAGE RESTRICTIONS

No transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals.

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

.