July 28, 2020 TIME: 2: 00 PM
TO: ALL TENNESSEE GAS PIPELINE COMPANY, L.L.C. CUSTOMERS
RE: SUCCESSFUL BIDDER FROM AVAILABLE FIRM CAPACITY (OPEN SEASON #1263)
Tennessee Gas Pipeline Company, L.L.C. (“Tennessee”) held an open season in accordance with Article XXVI, Section 5 of the General Terms and Conditions of its FERC Gas Tariff, which commenced at 8:15 AM on Tuesday, July 21, 2020 and closed at 4:00 PM on Monday, July 27, 2020. All final bids received in compliance with the terms and conditions of the open season were evaluated using the factors posted in the Open Season.
The winning bidder is not affiliated with Tennessee.
The winning bidder is as follows:
SERVICE REQUESTOR: SEQUENT ENERGY MANAGEMENT, L.P.
TERM: November 1, 2020 through October 31, 2022 DISCOUNTED: No VOLUME: 20,923 Dth/d RECEIPT POINT: 412180 – Iroquois/ TGP Shelton Interconnect F
DELIVERY: 420093 – Con Ed/ TGP White Plains NY Westches
NPV: $1,110,334.10
Total NPV: $1,110,334.10
For further information, please contact Marketing Representative:
Adam Ledet (713) 420-4813
Greg Pollard (713) 420-7149
Paul Gibson (713) 420-5128
Caitlin Harris (713) 420-2915
Scott Minear (713) 420-5177