Effective Evening Cycle (9:00) for the gas day of July 22, 2019 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 5 AND 6 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM
OFO DAILY ACTION ALERT FOR ZONE 0 FOR ALL BALANCING PARTIES FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM
OFO MONTHLY CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMSPA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· STA 9 (Segment 109 BH) - through 100% of SIPps increases due to scheduled maintenance and nominations in excess of operational capacity; 9,816 Dths
· Tres Pal/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SOP increases deliveries due to location off rate; 4,977 Dths
· Trnsco/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through approx 5% of SOP increases due to operational concerns; 2,151 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 53,776 Dths
· MLV 548 (Segment 542 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 7,308 Dths
· STA 307 (Segment 307 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 204 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 19,993 Dths
· STA 321 (Segment 321 FH) - through approx 44% of IT increases through a rate of .2461 due to nominations in excess of operational capacity; 8,665 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 53% of SIPss increases due to nominations in excess of operational capacity; 280,727 Dths
· Trnsco/TGP Rivervale New Jersey Ber Delivery Meter (Pin 420101) - through approx 74% of SOP increases due to nominations in excess of operational capacity; 164,207 Dths
· STA 224 (Segment 224 FH) / HC Zn 5 (Segment 299 FH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 256,633 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 551,494 Dths
LINEPACK RESTRICTIONS
No Payback or Lower Services OFF the pipe downstream of STA 237 on the 200 Line and downstream of STA 325 on the 300 Line
No Payback or Lower Services OFF the pipe South of STA 40
No Payback or Lower Services OFF the pipe in Zone 2
No Payback or Lower Services ON the pipe in Zone 4
STORAGE RESTRICTIONS
No Interruptible Storage Injection Services (IS-PA) at Bear Creek (460017) or Portland PA (460020).
No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (IS-PA, FS-PA).
Transfers into TGP Bear Creek from SNG Bear Creek will be allowed under the FS-PA Storage Service ONLY with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.