January 17, 2019
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2019 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***Sta 3A: Station Maintenance
***Completed
………………………………"
"***Sta 63: Replace compressor packing on unit 2D
100 Line Outages
"MLV 9-3D TO MLV 11-3: Pig run - Cleaning 5/21/19 - 5/24/19, Gauge 5/24/19, MFL 5/29/19
--5/21/19 through 5/29/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 13-3 TO MLV 17-3S: Pig run - Cleaning 5/7/19 - 5/10/19, Gauge 5/10/19, MFL 5/14/19, Hard Spot 5/16/19
--5/7/19 through 5/16/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 17-2 to MLV 9-2D: Pig runs - Chem Clean 9/12/19 - 9/18/19, Gauge 9/20/19, AFD 9/24/19, EMAT 9/26/19
--9/12/19 through 9/26/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 17-1 to MLV 14-1: Pig Run - Cleaning 7/15 - 7/20, Gauge 4/23, EMAT 7/24
--7/15/19 through 7/24/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 27A-101.3 TO MLV27A-102: Pig run - Cleaning 8/27/19, Gauge 8/27/19, MFL 8/29/19
--8/27/19 through 8/29/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 32-2D to MLV 40-2S: Wrinkle Bend
--10/15/19 through 10/24/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLVS 36-1: Pipe Replacement and Install New Valve
--1/15/19 through 3/8/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 40-3S to MLV 47-3: Make Piggable
--7/30/18 through 1/31/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Bear Creek Storage: Shut-in Test
--4/23/19 through 4/29/19: This project will require taking the facility out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
460017 STORAGE – BEAR CREEK
--10/15/19 through 10/21/19: This project will require taking the facility out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
"MLV 54-2D TO MLV 63-2S: Pig run - Cleaning 4/2/19 - 4/5/19, Gauge 4/5/19, MFL 4/16/19, Hard Spot 4/23/19
--4/2/19 through 4/23/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 54-2D TO MLV 63-2S: Pig run - AFD 4/10/19
--4/10/19 through 4/10/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Meter Station #2-0142: Replace Gate Valve
--TBD: This project will require taking the meter station out of service. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
420142 – CPTENTEX/TGP RULEVILLE MS SUNFLOWER
"MLV 71-4S TO MLV 63-4D: Pig Runs - Cleaning 2/28/19, Gauge 3/1/19, MFL 3/4/19, Hard Spot 3/7/19
--2/28/19 through 3/7/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 69-1R TO 69-1L: Pig run - Cleaning/Gauge 2/25/19, MFL 2/26/19
--2/25/19 through 2/26/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 79-2S TO MLV 71-2D: Pig run - Cleaning 3/11/19, Gauge 3/12/19, MFL 3/13/19, Hard Spot 3/19/19
--3/11/19 through 3/19/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 71-2D TO MLV 79-2S: Pig Runs - AFD 3/28/19
--3/28/19 through 3/28/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 78-4 TO MLV 71-4D: Pig run - Cleaning 3/15/19, Gauge 3/18/19, MFL 3/21/19, Hard Spot 3/26/19
--3/15/19 through 3/26/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 82-1 TO MLV 79-1D: Pig Runs - Cleaning 4/1/19, Gauge 4/2/19, Combo 4/3/19, Hard Spot 4/8/19, AFD 4/10/19, Caliper 4/12/19, MDS 4/15/19
--4/1/19 through 4/15/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 79-1D TO MLV 82-1: Pig Runs - AFD 4/10/19
"***MLVS 80A-100: Remediaton
--7/23/19 through 7/31/19: This activity will include pipe inspections and repairs, as needed, in specified areas. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
***Added
"***Sta 87: Unit 6C: Compressor Pistons and Rods Replacement
--1/22/19 through 2/1/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 96-1S TO MLV 87-1D: Pig Runs - Cleaning 7/9/19, Caliper 7/16/19, MDS 7/30/19
--7/9/19 through 7/30/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 96-2S to MLV 87-2D: Pig Runs - Caliper 7/18/19, MDS 8/1/19
--7/18/19 through 8/1/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 95-2 to MLV 87-2D: Pig Runs - Cleaning 6/5, AFD 6/12, EMAT 6/18
--6/5/19 through 6/18/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 106-1S TO MLV 96-1D: Pig run - Cleaning 4/2/19, MFL 4/4/19, Hardspot 4/9/19
--4/2/19 through 4/9/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 96-1D TO MLV 106-1S: Remediation
--5/22/19 through 6/1/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 106-1S TO MLV 96-1D: Pig Runs - AFD 6/4/19
--6/4/19 through 6/4/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 106-1D TO MLV 111-7R: Remediation
--4/29/19 through 5/18/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 110-2 TO MLV 106-2D: Pig run - Cleaning 3/18/19, Gauge 3/19/19, MFL 3/21/19, Hardspot 3/26/19
--3/18/19 through 3/26/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***Sta 107A : Unt 1A: BPS Upgrade
--1/7/19 through 1/18/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 1/7/19 to 1/11/19.
"MLV 113-3 to MLV 111-3: Pig Runs - Cleaning & Gauge 2/4, AFD 2/5, EMAT 2/7
--2/4/19 through 2/7/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLVS 117-1: ECDA
--7/8/19 through 7/20/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 121-2A to MLV 119-2: Pig run - Cleaning 8/20/19, MDS 8/21/19
--8/20/19 through 8/21/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
200 Line Outages
"Sta 204: Unit 1A: Repair Crankshaft
--9/17/18 through 2/15/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 209-1 TO MLV 204-1: Pig Runs - Cleaning/Gauge 9/10/19, MFL/AFD 9/12/19, Hardspot/EMAT 9/17/19
--9/10/19 through 9/17/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 209-2 TO MLV 204-2: Pig Run - Cleaning/Gauge 7/16/19, MFL/AFD 7/18/19, Hardspot/EMAT 7/23/19
--7/16/19 through 7/23/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 209-3 TO MLV 204-3: Pig Runs - Cleaning/Gauge 6/11/19, MFL/AFD 6/13/19, Hardspot/EMAT 6/18/19
--6/11/19 through 6/18/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 204-3 TO MLV 205-3: SCCDA
--6/17/19 through 6/29/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 204-4 TO MLV 205-4: SCCDA
--8/12/19 through 8/24/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***Sta 209: Unit 3A: Carbon Removal
--1/14/19 through 1/25/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 1/14/19 to 1/18/19.
"MLV 214-2 TO MLV 209-2: Pig Runs - Cleaning 4/3/19, Gauge 4/4/19, AFD 4/9/19
--4/3/19 through 4/9/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 214-4 to MLV 209-4: Pig Run - Cleaning/Gauge 5/14/19, MFL/AFD 5/16/19
--5/14/19 through 5/16/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***Sta 214: Unit 3: Compressor Maintenance
--12/13/18 through 1/25/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 12/13/18 to 1/11/19.
"MLV 214-1 to MLV 217-1: SCCDA
--4/15/19 through 4/27/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 219-1 TO MLV 214-1: Pig run - Cleaning 7/16/19, ILI 7/18/19
--7/16/19 through 7/18/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 219-1 TO MLV 214-1: Pig Run - Cleaning/Gauge 7/25/19, ILI 7/30/19, Hardspot 8/1/19
--7/25/19 through 8/1/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 218-2 to MLV 214-2: Pig Runs - Cleaning/Gauge 8/13/19, ILI 8/15/19
--8/13/19 through 8/15/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 219-2 TO MLV 214-2: Pig Run - ILI 8/20/19, Hardspot 8/22/19
--8/20/19 through 8/22/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 219-3 to MLV 214-3: Pig Run - Cleaning/Gauge 4/4/19, ILI 4/9/19, Hardspot 4/11/19
--4/4/19 through 4/11/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 219-4 TO MLV 214-4: Pig Run - Cleaning/Gauge 5/7/19, ILI 5/9/19
--5/7/19 through 5/9/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 217A-101.1 to MLV 217A-104: Pig Run - Cleaning/Gauge 5/30/19, ILI 6/4/19, Hardspot 6/6/19
--5/30/19 through 6/6/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 219-2 TO MLV 307-1: Remediaton
--4/8/19 through 5/27/19: This project will require taking the pipeline section out of service which will limit throughput and result in restrictions based on customer nominations. The meter listed below will likely experience fluctuations in flow and/or pressures. Potential out of path restrictions may be at risk.
420730 Nat Fuel Cranberry Del
"MLV 219-2B TO 220-2: Pig Run - Cleaning/Gauge 5/21/19, ILI 5/23/19
--5/21/19 through 5/23/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 219-3 TO MLV 307-2: Remediaton
--5/28/19 through 5/31/19: This project will require taking the pipeline section out of service which will limit throughput and result in restrictions based on customer nominations. The meter listed below will likely experience fluctuations in flow and/or pressures. Potential out of path restrictions may be at risk.
412871 Nat Fuel - Tionesta Rec
"MLVS 220-1: New Meter Tie-In - TGP/RH Energytrans Interconnect Meadville
--2/20/19 through 2/21/19: This activity will require operating at reduced pressures. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 230B-201 TO MLV 230B-204: Pig run - Cleaning & Gage 6/10, Combo 6/12
--6/10/19 through 6/12/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 230B-205 TO 230B-206: Pig run - Cleaning & Gage 6/17, Combo 6/19
--6/17/19 through 6/19/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta 241: Annual ESD test
--5/13/19 through 5/17/19: This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 245: Annual ESD test
--6/17/19 through 6/21/19: This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 245: Unit 1C: Borescope and Water Wash
--4/15/19 through 4/18/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
--9/30/19 through 10/4/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 245-1 to MLV 249-1: Pig run - Cleaning & Gage 6/24, Combo 6/26, Hard Spot 7/2
--6/24/19 through 7/2/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta 249: ESD Piping Modification & Filter Separator Maintenance
--4/15/19 through 4/20/19: This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 249-2 TO MLV 254-2: Pig Run - Cleaning/Gauge 5/13/19, Caliper 5/14/19, MFL 5/16/19
--5/13/19 through 5/16/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta 254: Filter Separator Maintenance
--4/22/19 through 4/27/19: This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 254-2 TO MLV 261-2: Pig Run - Cleaning/Gauge 6/4/19, Combo 6/6/19
--6/4/19 through 6/6/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 254-3 to MLV 258-3: Pig Run - Cleaning/Gauge 5/21/19, Combo 5/22/19
--5/21/19 through 5/22/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 265E-101.1 TO MLV 265E-104: Pig run - Cleaning/Gauge 4/1/19, Caliper 4/2/19, MFL 4/3/19
--4/23/19 through 4/25/19: This activity will require operating at controlled flow rates and will be coordinated with the customers. The meter listed below will be shut-in for the duration of the project. Potential in the path restrictions may be at risk.
420707 OCEAN ST/TGP PROVIDENCE
"267-1: Class Change
--5/10/19 through 8/10/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
300 Line Outages
"MLV 313-1 TO MLV 307-1: Pig Runs - Cleaning/Gauge 6/13/19, ILI 6/18/19, Hard Spot 6/20/19
--6/13/19 through 6/20/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLVS 313A-100: Remediaton
--6/3/19 through 6/6/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta 325: Unit 3A: Turbine Exchange
--5/6/19 through 5/12/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
400 Line Outages
"Sta 409A: Station Outage
--4/1/19 through 4/21/19: This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. The meter listed below will likely experience fluctuations in flow and/or pressures during this time. Potential In the Path nominations may be at risk.
450261 CENEGAS/TGP PEMEX DELIVERY
500 Line Outages
"Sta 40 to Sta 823: Maintenance Pig
--2/5/19 through 2/5/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The meters listed below will be shut-in for a brief period of time during the pig run. Potential out of path restrictions may be at risk.
420373 TRNSCO/TGP KINDER LA EXCH (BI 1
420708 ELIZ NG/TGP GRANT LA SALES ALLEN
420436 VERNON/TGP PITKIN LA VERNON
420793 ELIZ NG/TGP J R FRANKS 1 VERNON
420388 PROVNCAL/TGP PROVENCAL LA NATCHITOC
"***Sta 40 to Sta 823: Maintenance Pig
--10/8/19 through 10/8/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The meters listed below will be shut-in for a brief period of time during the pig run. Potential out of path restrictions may be at risk.
"Sta 504: Unit 2B: Controls upgrade & convert to simple cycle
--11/1/18 through 2/28/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLVS 528-1: Line Lowering
--11/5/18 through 1/31/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***MLV 534-2 TO MLV 538-2: Make Piggable
--MARCH through APRIL – Exact Dates TBD: This project will require taking the facility out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for approximately one month during the project. Potential out of path restrictions may be at risk.
420719 SPIREMS/TGP CAMP SHELBY FORREST
"***MLV 534-2 TO MLV 538-2: Pig run - Dates are tentative: Chem Cleaning 6/24/19 - 7/3/19, AFD 7/9/19, EMAT 7/11/19
--6/24/19 through 7/11/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations. The meter listed below will be shut-in for the Chem Cleaning and during the pig runs. Potential out of path restrictions may be at risk.
"***Sta 550: Unit 1A: Regrout
--6/4/18 through 1/18/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 6/4/18 to 1/15/19.
"MLV 555-1L TO MLV 558-1R: Remediaton
--5/1/19 through 5/21/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 555-2 TO MLV 559-2: Pig run - Cleaning 4/18/19, Gauge 4/19/19, MFL Combo 4/23/19
--4/18/19 through 4/23/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 557-3 TO MLV 559-3: Pig run - Cleaning 2/12/19, MFL Combo 2/14/19
--2/12/19 through 2/14/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 559-1 to MLV 565-1: Remediation
--5/22/19 through 6/17/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
800 Line Outages
"***MLV 847-1 TO MLV 851-1: Pig Run - Cleaning 4/18/19, Gauge 4/23/19, MFL Combo 4/25/19, Hardspot/EMAT 4/30/19
--4/18/19 through 4/30/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 8/13/19 to 8/19/19.
"MLV 860-1 TO MLV 856-1: Pig Runs - Cleaning/Gauge 3/14/19 & 3/19/19 & 3/21/19, MFL/AFD 3/26/19, Hardspot/EMAT 3/28/19
--3/14/19 through 3/28/19: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***Sta 871: Unit 3A: Compressor Valve Maintenance
--2/4/19 through 2/9/19: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
If you have any questions, please contact your Scheduler.