Effective Timely Cycle (9:00) for the gas day of October 16, 2018 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO Daily Critical Day 1 for all areas south of STA 9 for under-deliveries into the system and over-takes out of the system for all balancing parties
OFO Monthly Critical Day 1 for Zone 4 for LMS-PA's and SA's for over-deliveries into the system for all balancing parties
RESTRICTIONS
STA 409A (Segment 492 FH) – through 100% of SIPsp due to scheduled maintenance; 29,847 Dths
Donna Lateral (Segment 490 FH) – through 100% of SIPsp due to scheduled maintenance; 40,920 Dths
MLV 406 (Segment 406 BH) - through 100% of IT due to scheduled maintenance; 30 Dths
Tres Palacios Delivery Meter (Pin 421055) – through approx 22% of SOP due to imbalance management; 40,988 Dths
Transco Kinder Deliver Meter (Pin 420373) - through approx 56% of SOP due to imbalance management; 141,777 Dths
Heidelberg Delivery Meter (Pin 420291) – through 100% of SIPps due to imbalance management; 1,375 Dths
STA 224 (Segment 224 FH) / HC Zn 5 (Segment 299 FH) – through approx 86% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 499,978 Dths
Honeoye Storage Meter (Pin 420526) – through approx 48% of SOP deliveries due to nominations in excess of operational capacity; 47,650 Dths
STA 245 (Segment 245 FH) – through approx 92% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 482,103 Dths
Mendon Delivery Meter (Pin 420285) – through 100% of SOP receipts due to displacement gas unavailable for backhaul; 7,500 Dths
STA 307 (Segment 307 BH) – through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 5,000 Dths
MLV 314 (Segment 314 BH) – through approx 79% of SOP due to nominations in excess of operational capacity; 74,616 Dths
STA 315 (Segment 315 BH) – through 100% of SOP due to force majeure event at STA 317 and nominations in excess of operational capacity; 152,001 Dths
Mahwah Delivery Meter (Pin 420207) – through approx 91% of SOP due to nominations in excess of operational capacity; 294,025 Dths
Rivervale Delivery Meter (Pin 420101) – through approx 99% of SIPss due to nominations in excess of operational capacity; 9,992 Dths
MLV 355 (Segment 355 BH) – through 100% of SOP due to operational concerns; 53,135 Dths
LINEPACK RESTRICTIONS
Marcellus Area – through 100% of payback to TGP; 10,000 Dths
STORAGE RESTRICTIONS
No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (IS-PA, FS-PA)
Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND
ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED
SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.