FORCE MAJEURE AT STATION 1 AND STATION 9 UPDATE #5
In accordance with Article XII of Tennessee Gas Pipeline Company, LLC's (“Tennessee”) FERC Gas Tariff, Tennessee declared a Force Majeure event at Station 1 (located near Agua Dulce) and at Station 9 (located near Victoria, TX) on June 15, 2018 (Notice Identifier 367831) due to identified anomalies that necessitated repairs in the section of the pipe between Station 1 and Station 9. MLV 7 to Station 9 is now back in service. Work continues at Station 1 to MLV 7. Anticipated return to service for this section of pipe is now estimated to be October 15, 2018.
Tennessee will post more updates as repairs are completed for the remaining affected sections of the pipe.
Please contact your Scheduler or Account Representative if you have any questions.