Effective ID1 Cycle (14:00) for the gas day of July 23, 2018 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO Daily Balancing Alert Meter Specific for Pin 421017 for over-takes out of the system
OFO Daily Critical Day 1 for all areas south of STA 9 for under-deliveries into the system and over-takes out of the system for all balancing parties
OFO Daily Critical Day 1 for Zone 4 for over-deliveries into the system and under-takes out of the system for all balancing parties
OFO Monthly Critical Day 1 for Zone 4 for LMS-PA's and SA's for over-deliveries into the system for all balancing parties
RESTRICTIONS
STA 1 (Segment 101 BH) – through 100% of IT ID1 increases due to the force majeure event at Sta 1 and Sta 9; 30 Dths
MLV 834 (Segment 834 BH) - through approx 18% of SOP ID1 increases due to nominations in excess of operational capacity; 12,752 Dths
STA 114 (Segment 114 BH) – through 100% of SIPps ID1 increases due to scheduled maintenance; 585 Dths
STA 204 (Segment 204 BH) – through 100% of SOP ID1 increases due to scheduled maintenance; 35,000 Dths
STA 237 (Segment 237 FH) – through 100% of SOP ID1 increases due to nominations in excess of operational capacity; 48,187 Dths
STA 245 (Segment 245 FH) – through approx 89% of SOP ID1 increases due to scheduled maintenance and nominations in excess of operational capacity; 240,984 Dths
STA 230C (Segment 296 FH) – through 100% of IT ID1 increases due to scheduled maintenance; 503 Dths
MLV 314 (Segment 314 BH) – through approx 85% of SOP ID1 increases due to nominations in excess of operational capacity; 76,768 Dths
STA 315 (Segment 315 BH) – through 100% of PIP ID1 increases due to scheduled maintenance and nominations in excess of operational capacity; 121,946 Dths
STA 325 (Segment 324 FH) - through 100% of SOP ID1 increases due to emergent repair and nominations in excess of operational capacity; 151,325 Dths
MLV 355 (Segment 355 BH) – through 100% of SOP ID1 increases due to nominations in excess of operational capacity; 26,475 Dths
LINEPACK RESTRICTIONS
None
STORAGE RESTRICTIONS
No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (IS-PA, FS-PA)
Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND
ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED
SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.