Effective Timely Cycle (9:00) for the gas day of June 18, 2018 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO Daily Balancing Alert Meter Specific for Pin 421017 for over-takes out of the system
OFO Daily Critical Day 1 for all areas south of STA 9 for under-deliveries into the system and over-takes out of the system for all balancing parties
OFO Daily Critical Day 1 for Zone 4 for over-deliveries into the system and under-takes out of the system for all balancing parties
OFO Daily Critical Day 1 for zones 5 & 6 downstream of STA 245 and STA 325 for under-deliveries into the system and over-takes out of the system for all balancing parties
OFO Monthly Critical Day 1 for all of Zone 4 for LMS-PA and SA Balancing Parties
RESTRICTIONS
MLV 406 (Segment 406 BH) – through 100% of SOP due to operational concerns; 9,898 Dths
STA 1 (Segment 101 BH) – through 100% of SIPps due to the force majeure event at Sta 1 and Sta 9; 14,791 Dths
STA 9 (Segment 109 BH) – through approx 7% of PIP due to the force majeure event at Sta 1 and Sta 9; 41,781 Dths
MLV 834 (Segment 834 BH) - through approx 28% of SOP due to nominations in excess of operational capacity; 95,092 Dths
STA 87 (Segment 860 BH) – through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 40,258 Dths
STA 114 (Segment 114 BH) – through 100% of SIPps due to scheduled maintenance; 162 Dths
STA 204 (Segment 204 BH) – through 100% of SOP due scheduled maintenance; 136,944 Dths
STA 224 (Segment 224 FH) / HC Zn 5 (Segment 299 FH) – through approx 58% of SOP due to nominations in excess of operational capacity; 398,043 Dths
STA 245 (Segment 245 FH) – through 100% of SOP due to the emergent repair at Sta 245; 357,717 Dths
STA 261 Suction (Segment 260 FH) – through 100% of SOP due to scheduled maintenance; 54,862 Dths
Town of Pembroke Delivery Meter (Pin 47591) – through approx 91% of IT due to nominations in excess of operational capacity; 37,113 Dths
STA 315 (Segment 315 BH) – through 100% of SOP due to the emergent repair at Sta 315; 165,271 Dths
STA 321 (Segment 321 FH) - through approx 62% of SOP due to nominations in excess of operational capacity; 474,712 Dths
STA 325 (Segment 324 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 377,081 Dths
MLV 355 (Segment 355 BH) – through approx 68% of SOP due to nominations in excess of operational capacity; 104,187 Dths
LINEPACK RESTRICTIONS
South of STA 17 on 100 Line – through 100% of payback from TGP; 276 Dths
STORAGE RESTRICTIONS
No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (IS-PA, FS-PA)
Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND
ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED
SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.