May 17, 2018
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2018 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***MLV 17-1S to MLV 20-1: Pig runs - Cleaning/Gauge 5/8/18, Cleaning/Gauge 5/9/18, MFL 5/10/18, Hard Spot 5/15/18
***Completed
………………………………"
"***MLVS 31-1: Remediation
"***MLVS 83-2: Remediation
"***Sta 200: Annual ESD Test
"***Sta 230C: Annual ESD Test
"***Sta 245: Unit 1C: Unit Maintenance
"***MLV 245-2D to MLV 249-2: Pig runs - Cleaning / Gauge 5/8/18, Combo 5/9/18
"***MLV 254-2 to MLV 261-2: Pig runs - Cleaning / Gauge 5/14/18, AFD 5/16/18
"***Sta 264: Unit 1C: Turbine Exchange
"***Sta 266A: Crane Load Testing
"***MLV 313 to MLV 237: Efficiency Pig
"***Sta 405A: Annual ESD Test
"***Sta 409A: Annual ESD Test
100 Line Outages
"Sta 1: Annual ESD Test
--7/8/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 1-1D to MLV 9-1S: Remediation
--1/18/18 through 6/15/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project. Potential in the path restrictions may be at risk.
"Sta 3A: New Station Tie-In (100-2 line)
--6/1/18 through 6/8/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 5-2 to MLV 8-2: Pig runs - Cleaning 7/9/18, Cleaning 7/18/18, Gauge 7/19/18, MFL 7/24/18, Hard Spot 7/26
--7/9/18 through 7/26/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 10-1 to MLV 12-1: Pressure Weld Replacement
--4/14/18 through 6/15/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 11A: New Station Tie-In (100-1 line)
--5/1/18 through 6/15/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 11A: New Station Tie-In (100-2 line)
--6/18/18 through 6/25/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLVS 14E-100: Line Lowering
--5/16/18 through 5/24/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
410144 CPNOPROC/TGP UDP HCP COLORADO
"MLVS 15A-100: Drip Removal
--5/25/18 through 5/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
420162 COKINOS/TGP RAUN FARM 2 TX COLORAD
420479 COKINOS/TGP CATTLE TX FARM WHARTON
412023 HGI/TGP UDP ENGLEHARDT COLORADO
"MLV 17-2S to MLV 20-2: Pig runs - Cleaning 6/12/18, Gauge 6/13/18, Geometry 6/19/18, MFL 6/21/18
--6/12/18 through 6/21/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 17-3D to MLV 20-3: Pig runs - Cleaning 5/22/18, Gauge 5/23/18, MFL 5/31/18
--5/22/18 through 5/31/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***Sta 25: Station Maintenance: Electrical Inspection
--6/12/18 through 6/13/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 5/16/18 to 5/17/18.
"MLV 32-1 to MLV 34-1: Spike Test
--6/4/18 through 7/27/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLVS 36-1: Pipe Replacement and Install New Valve
--1/7/19 through 3/1/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLVS 36-2: Pipe Replacement and Install New Valve
--10/22/18 through 12/28/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLVS 36-3: Pipe Replacement and Install New Valve
--8/13/18 through 10/19/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 40-1D to MLV 47-1: Pig runs - Cleaning & Gauge 7/10/18-7/13/18, DEF Inspection 7/17/18, TDW MDS 7/19/18
--7/10/18 through 7/19/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 40-3S to MLV 47-3: Make Piggable
--9/10/18 through 11/30/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Beer Creek Storage: Shut In Test
--10/16/18 through 10/23/18: This project will require taking the facility out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
460017 STORAGE – BEAR CREEK
"MLV 42-2 to MLV 47-2: Pig runs - Cleaning & Gauge 6/5/18-6/8/18, DEF Inspection 6/12/18, TDW MDS 6/14/18
--6/5/18 through 6/14/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 54-4 to MLV 63-4: Pig runs - AFD 9/24/18, EMAT 10/4/18
--9/24/18 through 10/4/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 63-1 to MLV 69-1: Pig runs - Chem Cleaning 6/4/18 to 6/16/18, AFD 7/3/18, EMAT 7/5/18
--6/4/18 through 7/5/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 63-1 to MLV 69-1: Pig runs - MFL 8/2/18, Hard Spot 8/7/18
--8/2/18 through 8/7/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 63-3 to MLV 71-3: Pig runs - Chem Cleaning 7/20/18, Gauge Plate 7/23/18, Caliper 7/24/18, MDS 7/26/18
--7/20/18 through 7/26/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 63-4D to MLV 71-4: Pig runs - AFD 10/6/18, EMAT 10/25/18
--10/6/18 through 10/25/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***MLVS 65-1: Remediation
--2/1/18 through 5/21/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 2/1/18 to 5/15/18.
"MLV 77-1 to MLV 79-1: Pig runs - Chem Cleaning 8/13/18, AFD 8/14/18, EMAT 8/16/18
--8/13/18 through 8/16/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta 87: Unit 1E: Unit Maintenance
--6/18/18 through 7/13/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 96: Sub-Station: Inspection
--5/21/18 through 5/26/18: This project will require a building outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 96: Unit 2D: Electrical Panel Replacement
--5/14/18 through 6/1/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 106-3D to MLV 200-1S: Remediation
--5/11/18 through 5/25/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 106: Unit 1C: Unit Maintenance
--4/2/18 through 7/27/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLVS 107-7: Remediation
--5/7/18 through 5/17/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 110: Annual ESD Test
--6/18/18 through 6/22/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 110-2 to MLV 114-2: Pig runs - Cleaning / Gauge 7/10/18, MFL 7/12/18, Hard Spot Tool 7/17/18
--7/10/18 through 7/17/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The meters listed below will be shut-in for a brief period of time during the pig run. Potential out of path restrictions may be at risk.
412742 BIGSANDY/TGP GLANCY CARTER
"MLV 110-6 to MLV 114-6: Pig runs - Cleaning / Gauge 7/9/18, MFL 7/19/18
--7/9/18 through 7/19/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***MLVS 111-2: Pipeline Maintenance
--5/7/18 through 5/22/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 5/7/18 to 5/19/18.
"MLV 111-3 to MLV 114-3: Pig runs - Cleaning & Gauge Tool 10/10/18, AFD Tool 10/16/18, EMAT 10/18/18
--10/10/18 through 10/18/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***MLVS 118-3: Make Piggable
--6/18/18 through 7/30/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled 6/4/18 to 7/16/18.
"***Sta 114: Unit 1C: Unit Inspection
--5/21/18 through 5/25/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled 5/14/18 to 5/19/18.
"***Sta 114: Unit 2C: Unit Inspection
--5/7/18 through 5/17/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled 5/7/18 to 5/12/18.
200 Line Outages
"MLV 200-1D to MLV 200-1A: Drip Removal
--6/6/18 through 6/13/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 200-2D to MLV 204-2: Pig runs - Caliper 7/12/18, MFL 7/19/18
--7/12/18 through 7/19/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 200-3A to MLV 200-3: Pig runs - Cleaning / Gauge 5/15/18, MFL 5/17/18, Hard Spot Tool 5/22/18
--5/15/18 through 5/22/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta 204: Unit 2A: Unit Maintenance
--5/15/18 through 5/17/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 204: Unit 8A: Unit Maintenance
--5/16/18 through 5/18/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 204: Unit 12A: Unit Maintenance
--5/4/18 through 5/19/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 204-2D to MLV 205-2: Drip Removal
--5/29/18 through 6/5/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 204-4BL to MLV 205-4: Drip Removal
--5/21/18 through 5/28/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 204-4 to MLV 209-4: Pig runs - Cleaning / Gauge 8/14/18, MFL 8/16/18
--8/14/18 through 8/16/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta 209: Unit 1A: Foundaton Repair
--4/2/18 through 7/13/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 209-1 to MLV 214-1: Pig runs - Cleaning / Gauge 6/21/18, MFL 6/26/18, Hard spot 6/28/18
--6/21/18 through 6/28/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The meter listed below will be shut-in for a brief period of time during the pig run. Potential in the path restrictions may be at risk.
47652 UTICA EO/TGP LEESVILLE PROC PLNT CA
"MLV 209-3 to MLV 214-3: Pig runs - Cleaning / Gauge 7/24/18, MFL 7/26/18, Hard spot 7/31/18
--7/24/18 through 7/31/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta 209: Unit Maintenance
--3/19/18 through 5/18/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 214: Annual ESD Test
--5/21/18 through 5/28/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"218-2 to 219-2: Pipe Replacement
--9/17/18 through 9/28/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 217A-201.3 to MLV 217A-202.3: Pig runs - Cleaning / Gauge 6/5/18, MFL 6/8/18
--6/5/18 through 6/8/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLVS 217: New Meter Hot Taps for Hickory Run
--7/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 219-2D to MLV 307-1: Pig runs - Cleaning / Gauge 10/19/18, AFD 10/23/18, EMAT 10/25/18
--9/25/18 through 10/25/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 224-1 to MLV 229-1: Pig runs - Cleaning / Gauge 9/11/18, MFL 9/13/18
--9/11/18 through 9/13/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 230-1 to MLV 237-1: Remediation
--9/17/18 through 10/5/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"230B-101 TO 230B-106: Make Piggable
--7/9/18 through 7/18/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
--8/7/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"230B-201 TO 230B-206A: Make Piggable
--7/19/18 through 7/28/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
--8/14/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 230C: Unit 2A: Unit Maintenance
--5/14/18 through 5/18/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 233: Annual ESD Test
--6/5/18 through 6/6/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 237: Unit 1A: Unit Maintenance
--6/11/18 through 6/14/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 237-2 to MLV 238-2: SCCDA
--8/6/18 through 8/17/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 313A-405A to MLV 313A-409: Replace Actuators
--9/17/18 through 9/22/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential in the path restrictions may be at risk.
420644 NYSEG/TGP PRATTSBURG SALES STEUBEN
420746 NYSEG/TGP WALLACE SALES STEUBEN
"Sta 241: Annual ESD Test
--5/17/18 through 5/25/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 241: Unit 1A: Unit Maintenance
--5/21/18 through 5/25/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 241: Unit 1B: Unit Maintenance
--6/4/18 through 6/15/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 241: Unit 2B: Unit Maintenance
--5/21/18 through 6/1/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 245: Annual ESD Test
--6/11/18 through 6/15/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 249: Unit 1A: Unit Maintenance
--6/18/18 through 6/29/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 249: Unit 2A: Unit Maintenance
--7/9/18 through 7/20/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 252-1 to MLV 252-1: Pressure Test
--9/5/18 through 10/19/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 254: Annual ESD Test
--5/17/18 through 5/27/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 254: Station Automation and Maintenance
"MLV 254-1 to MLV 261-1: Remediation - Phase 1
--4/2/18 through 6/10/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 254-2 to MLV 261-2: Pig runs - Cleaning 10/22/18, EMAT 10/24/18
--10/22/18 through 10/24/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta 254: Building A: Automation Upgrade - 2 weeks/unit - up to 2 units may be down at a same time
--5/28/18 through 7/28/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 254: Unit 2A: Unit Maintenance
--3/5/18 through 6/30/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 254: Unit 2B: Unit Maintenance
"Sta 261: Automation Upgrade
--10/1/18 through 10/23/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 261: A Building: BPS Upgrade
--8/20/18 through 8/30/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta 261: C Building: BPS Upgrade
--9/10/18 through 9/21/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled 9/4/18 to 9/13/18.
"Sta 261: D Building: BPS Upgrade
--6/11/18 through 6/21/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 261: D Building: Silencer Replacement
--6/4/18 through 6/25/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 261BP-101-BERKSHIRE POWER DELIVERY: 1000 - 0+00 to MLV 261BP-101-BERKSHIRE POWER DELIVERY: ECDA
--6/18/18 through 6/25/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
420901 SHELL/TGP BERKSHIRE POWER SALES HAM
"Sta 261: Unit Maintenance: Water Wash
--9/10/18 through 9/14/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 261: Unit Maintenance: Boroscope Maintenance
--9/11/18 through 9/13/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta 261; Unit 4A: Automation Upgrade
--8/20/18 through 9/7/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled 8/20/18 to 9/2/18.
"Sta 261: Unit 4A: Compressor Maintenance
--9/11/18 through 9/14/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 264: Annual ESD Test
--6/6/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 264: Unit 1C: Maintenance Upgrade & Protective Devices
--5/29/18 through 5/30/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 264: Unit Maintenance: Water Wash
--9/12/18 through 9/13/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta 264: Unit 2C: Turbine Exchange
***Date Change, Previously scheduled 5/14/18 to 5/18/18.
"Sta 264: Unit 2C: Protective Devices
--5/31/18 through 6/1/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 264: Unit Maintenance: Boroscope Maintenance
--9/18/18 through 9/19/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 265E-201 to MLV 265E-202: Pressure Test
--7/30/18 through 8/9/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
420758 – NARNGST/TGP LINCOLN SMS PROVIDENCE
"Sta 265E: 4000 hr Inspection
--5/5/18 through 5/18/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"265E: 4000 hr Inspection
--11/5/18 through 11/15/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 266A: Annual ESD Test
--10/1/18 through 10/5/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 266C-101.1 to MLV 266C-102: Pig runs - Cleaning / Gauge 6/19/18, Combo 6/20/18
--6/19/18 through 6/20/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta 266A: Unit 1B: 4000 hr Inspection
--6/11/18 through 6/15/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 267: Annual ESD Test
--8/21/18 through 8/22/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"267-1: Class Change
--5/10/19 through 7/10/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 267-1 to MLV 270C-101.1: Pig runs - Cleaning / Gauge 5/29/18, Combo 5/30/18, Hard Spot Tool 6/4/18
--5/29/18 through 6/4/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 268A-301 to MLV 268A-302: Pressure Test
--7/9/18 through 7/19/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
420111 – BOSTN/TGP LEOMINSTER MA WORCHESTER
"MLV 270C-101 to MLV 270C-102: Remediation
--5/7/18 through 6/16/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 270C-501 to MLV 270C-502: Remediation
--5/14/18 through 5/23/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 270B: Annual ESD Test
--10/23/18 through 10/25/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 270B-101.1 to MLV 270B-102: Pig runs - Cleaning / Gauge 6/6/18, Combo 6/7/18, Hard Spot Tool 6/12/18
--6/6/18 through 6/12/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 270B-103 to MLV 270B-104: Pig runs - Cleaning / Gauge 5/22/18, Combo 5/23/18
--5/22/18 through 5/23/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 273B-101 to MLV 273B-102: Remediation
--5/21/18 through 5/26/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 273C-101 to MLV 273C-103: Remediation
--5/29/18 through 6/12/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
300 Line Outages
"Sta 303A: Unit 1A: Unit Maintenance
--5/21/18 through 6/1/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta 310: Annual ESD Test
--6/5/18 through 6/6/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Added
"***Sta 313 to Sta 307: Maintenance Pig
--6/5/18 through 6/6/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 313-1 to MLV 317-1: Remediation
--7/23/18 through 8/10/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 313: Dehy System: Maintenance
--5/18/18 through 5/31/18: This project will require taking the facility out of service. This will result in no withdrawals out of Hebron Storage during this period.
"Sta 315: Station Electrical Maintenance
--6/14/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 315-2 to MLV 317-2: Remediation
--8/13/18 through 8/17/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 317-1BL to MLV 319-1: Remediation
--6/4/18 through 6/8/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 317: Unit 1B: Compressor Maintenance
--6/4/18 through 7/31/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 317: Unit 1B: Electric Company Outage
--6/8/18 through 6/11/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 319-1 to MLV 321-1: Remediation
--5/29/18 through 6/15/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLVS 319: Meter Tie-In
--5/16/18 through 5/18/18: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 321-1 to MLV 325-1: Remediation
--6/18/18 through 7/20/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
400 Line Outages
"MLV 400-2 (STATION 1) to MLV 409-2: Remediation
--6/11/18 through 6/29/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLVS 407D-300: Line Lowering
--5/21/18 through 6/30/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
420913 MISSIONP/TGP TABASCO #2 DELIVERY BI
412562 MISSIONP/TGP TABASCO #2 RECEIPT BID
412656 FIDELITY/TGP TABASCO WEST HIDALGO
"MLV 409A-101 TO MLV 409A-103: Remediation
--6/25/18 through 7/13/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 409A-901 to MLV 409A-902: Pig runs - Maintenance 6/19/18, Gauge 6/20/18, MFL 6/28/18
--6/19/18 through 6/28/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
500 Line Outages
"Sta 507F to Sta 823: Pig run - Maintenance/Brush 9/11/18
--9/11/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLVS 522-1: Repair Line Covering
--9/1/18 through 9/15/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 527: Vessel Valve Replacement
--6/25/18 through 7/2/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLVS 528-1: Line Lowering
--9/15/18 through 10/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 529-1 to MLV 530-1: Pig runs - Cleaning 5/22,23,24 Caliper 5/29/18, ILI 5/31/18
--5/23/18 through 5/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 530-3 to MLV 532-2: Remediation
--6/11/18 through 6/27/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 538-1 to MLV 542-1: Remediation
--7/9/18 through 7/16/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 542: Station Maintenance
--9/10/18 through 9/14/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 542: Annual ESD Test
--9/17/18 through 9/18/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 542: Unit 1B: Unit Maintenance
--6/18/18 through 7/6/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 546: Annual ESD Test
--10/17/18 through 10/18/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 546: Unit 1A: Unit Maintenance
--6/11/18 through 6/22/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 546: Unit 2A: Unit Maintenance
--6/25/18 through 7/6/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 546: Unit 4A: Unit Maintenance
--7/30/18 through 8/10/18: This project will require a unit outage, which could limit throughput through the station and result in restrictionThis project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.s based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 549-3 to MLV 550-3: ILI Only
--8/7/18 through 8/8/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta 550: A Building: Valve Maintenance
--6/4/18 through 6/13/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta. 550-1A: Unit Maintenance
--8/15/17 through 6/1/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 555: Annual ESD Test
--5/14/18 through 5/20/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 561-1 to MLV 563-1: Pressure Test
--6/11/18 through 7/13/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 561-1 to MLV 563-1: Tethered ILI
--6/27/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***MLVS 560-2: Modify Crossover - 560-2 to 561-2
--5/28/18 through 6/2/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLVS 560-2: Install Valve on Crossover - 562-2 to 563-2
--6/2/18 through 6/8/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLVS 560-2: Prepare 500-1 for Hydrotest - 560-1 to 561-1
--6/6/18 through 6/11/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLVS 560-2: Prepare 500-1 for Hydrotest - 562-1 to 563-1
--6/11/18 through 6/15/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLVS 560-2: Prepare 500-1 for Hydrotest - PT 561-1 to 562-1
--6/6/18 through 7/2/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLVS 560-2: Reconnect Hydrotest Segment - 560-1 to 561-1
--6/30/18 through 7/5/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLVS 560-2: Reconnect Hydrotest Segment 562-1 to 563-1
--7/5/18 through 7/9/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 561-1 to MLV 563-1: ECDA
"Sta 563: Tie-In to 500-1, 500-2, & 800-1
--6/6/18 through 7/6/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
700 Line Outages
"MLV 700-1 to MLV 706-1: Pig runs - Cleaning / Gauge 9/17/18 - 9/19/18, Combo 9/20/18, Hard Spot Tool 9/24/18
--9/17/18 through 9/24/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
800 Line Outages
"Sta 820-1 to Sta 823: Pig run - Maintenance/Brush 7/10/18
--7/10/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta 823 to MLV 516: Pig run - Maintenance/Brush 6/19/18
--6/19/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta 823: Purchase Power Conversion
--8/27/18 through 8/30/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Higher than normal pressures in the area are probable during this outage. Potential out of path restrictions may be at risk.
"Sta 823 to Sta 40: Pig run - Maintenance/Brush 5/22/18
--5/22/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The meters listed below will be shut-in for a brief period of time during the pig run. Potential out of path restrictions may be at risk.
420373 TRNSCO/TGP KINDER LA EXCH (BI 1
420708 ELIZ NG/TGP GRANT LA SALES ALLEN
420436 VERNON/TGP PITKIN LA VERNON
420793 ELIZ NG/TGP J R FRANKS 1 VERNON
420388 PROVNCAL/TGP PROVENCAL LA NATCHITOC
"Sta 827 to Sta 823: Pig run - Maintenance/Brush 6/6/18
--6/6/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 834-1 to MLV 835-1: Spike Test
--4/17/18 through 5/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
412691 REGENCY/TGP PEOPLES ROAD FRANKLIN
49554 – AM MIDLA/TGP NORTH PEOPLES RD FRANK
420279- ATMOS TL/TGP CROWVILLE LA FRANKLIN
Note: The receipts cannot exceed deliveries in MLV 836-1 to MLV 846-1 section.
"MLV 843-1 to MLV 847-1: Pig runs - Cleaning 6/14/18, Gauge Plate 6/15/18, MFL 6/18/18, Hard Spot 6/22/18
--6/14/18 through 6/22/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 846-1 to MLV 847-1: Hydrotest
--4/17/18 through 5/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
420328 – ATMOS-MS/TGP HARDY STA MS GRENADA
"MLV 851-1 to MLV 852-1: Spike Test
--7/16/18 through 9/3/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 851-1: Drip Removal and Install New Valve
--9/3/18 through 9/21/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 856-1 to MLV 859-1: Pig runs - Cleaning 7/10/18, Gauge 7/11/18, MFL 7/12/18, Hard Spot 7/17/18
--7/10/18 through 7/17/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta 860: Annual ESD Test
--6/19/18 through 6/20/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 866-1D to MLV 871-1: Remediation
--7/9/18 through 7/20/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 871-1 to MLV 876-1: Remediation
--7/23/18 through 8/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
If you have any questions, please contact your Scheduler.