Effective Evening Cycle (9:00) for the gas day of April 20, 2018 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO Daily Critical Day 1 for all areas south of STA 9 for under-deliveries into the system and over-takes out of the system for all balancing parties
Monthly OFO Critical Day 1 for all of Zone 4 for LMS-PA and SA Balancing Parties
RESTRICTIONS
STA 9 (Segment 109 BH) – through 100% of PIP EC increases due to scheduled maintenance; 24,971 Dths
STA 224 (Segment 224 FH) / HC Zn 5 (Segment 299 FH) – through 100% of SOP EC increases due to nominations in excess of operational capacity; 797,734 Dths
STA 245 (Segment 245 FH) – through 100% of PIP EC increases due to scheduled maintenance and nominations in excess of operational capacity; 271,458 Dths
STA 261 Discharge (Segment 261 FH) – through 100% of SOP EC increases due to scheduled maintenance and nominations in excess of operational capacity; 83,378 Dths
STA 267 (Segment 266 FH) – through approx 64% of SOP EC increases due to nominations in excess of operational capacity; 8,448 Dths
Fitchburg to Gloucester (Segment 268 FH) - through 100% of SOP EC increases due to nominations in excess of operational capacity; 8,875 Dths
MLV 273 (Segment 284 FH) - through approx 87% of SOP EC increases due to nominations in excess of operational capacity; 53,153 Dths
STA 315 (Segment 315 BH) – through 100% of SOP EC increases due to scheduled maintenance and nominations in excess of operational capacity; 127,335 Dths
STA 321 (Segment 321 FH) - through approx 72% of SOP EC increases due to nominations in excess of operational capacity; 306,450 Dths
STA 325 (Segment 324 FH) - through 100% of PIP EC increases due to scheduled maintenance and nominations in excess of operational capacity; 306,359 Dths
Rivervale Delivery Meter (Pin 420101) – through approx 77% of SOP EC increases due to nominations in excess of operational capacity; 7,652 Dths
MLV 336 (Segment 336 FH) – through approx 96% of SOP EC increases due to nominations in excess of operational capacity; 73,150 Dths
LINEPACK RESTRICTIONS
DS of 237 – through 100% of payback from TGP; 5,000 Dths
STORAGE RESTRICTIONS
No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (IS-PA, FS-PA)
Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE EC INCREASES DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND
ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED
SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.