Effective Evening Cycle (9:00) for the gas day of March 21, 2018 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO Daily Critical Day 1 for all areas south of STA 9 for under-deliveries into the system and over-takes out of the system for all balancing parties
OFO Daily Critical Day 1 for DS of STA 254 on the 200 Line for under-deliveries into the system and over-takes out of the system for all balancing parties
RESTRICTIONS
MLV 406 (Seg 406 BH) – through 100% of SIPsp EC increases due to scheduled maintenance; 4,395 Dths
STA 1 (Segment 101 BH) – through 100% of SOP EC increases due to scheduled maintenance; 3,082 Dths
STA 9 (Segment 109 BH) – through 100% of SIPsp EC increases due to scheduled maintenance; 54,967 Dths
STA 224 (Segment 224 FH) / HC Zn 5 (Segment 299 FH) – through approx 99% of SOP EC increases due to nominations in excess of operational capacity; 597,468 Dths
STA 237 (Segment 237 FH) – through approx 53% of SOP EC increases due to nominations in excess of operational capacity; 5,615 Dths
STA 245 (Segment 245 FH) – through approx 99% of SOP EC increases due to nominations in excess of operational capacity; 405,472 Dths
Wright Receipt Meter (Pin 412181) – through approx 82% of SOP EC increases due to nominations in excess of operational capacity; 150,270 Dths
STA 261 Discharge (Segment 261 FH) – through 100% of SOP EC increases due to nominations in excess of operational capacity; 123,386 Dths
STA 267 (Segment 266 FH) - through approx 98% of SOP EC increases due to nominations in excess of operational capacity; 61,457 Dths
Fitchburg to Gloucester (Segment 268 FH) - through 100% of SOP EC increases due to nominations in excess of operational capacity; 19 Dths
MLV 273 (Segment 284 FH) – through approx 93% of SOP EC increases due to nominations in excess of operational capacity; 150,107 Dths
STA 315 (Segment 315 BH) – through 100% of SOP EC increases due to scheduled maintenance; 112,243 Dths
STA 321 (Segment 321 FH) - through approx 91% of SOP EC increases due to nominations in excess of operational capacity; 391,202 Dths
STA 325 (Segment 324 FH) - through approx 96% of SOP EC increases due to nominations in excess of operational capacity; 211,487 Dths
Mahwah Delivery Meter (Pin 420207) – through approx 98% of SOP EC increases due to nominations in excess of operational capacity; 9,179 Dths
Rivervale Delivery Meter (Pin 420101) – through 100% of SOP EC increases due to nominations in excess of operational capacity; 24,958 Dths
MLV 336 (Segment 336 FH) – through 100% of SOP EC increases due to nominations in excess of operational capacity; 39,600 Dths
LINEPACK RESTRICTIONS
Downstream of STA 237 – through 100% of payback from TGP; 5,000 Dths
STORAGE RESTRICTIONS
No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (IS-PA, FS-PA)
Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR
CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND
ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED
SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.