February 22, 2018
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2018 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***Sta 200: Unit 12A: Unit Maintenance
***Completed
………………………………"
"***Sta 204: Unit 5A: Engine Maintenance
"***MLV 856-1: Trap Modification
100 Line Outages
"MLV 1-1D to MLV 9-1S: Remediation
--1/18/18 through 3/10/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project. Potential in the path restrictions may be at risk.
421083 – DEVON GS/TGP PORT OF VICTORIA: DIP
"MLV 1-2 to MLV 5-2: Pig runs - Cleaning 5/15/18, Cleaning 5/18/18, Gauge 5/21/18, MFL 5/25/18
--5/15/18 through 5/25/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 2-1 to MLV 4-1: Pressure Weld Replacement
--3/15/18 through 5/1/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project. Potential in the path restrictions may be at risk.
"Sta 3A: New Station Tie-In (100-1 line)
--3/15/18 through 4/30/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 3A: New Station Tie-In (100-2 line)
--5/7/18 through 5/14/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 5-2 to MLV 8-2: Pig runs - Cleaning 7/9/18, Cleaning 7/18/18, Gauge 7/19/18, MFL 7/24/18, Hard Spot 7/26
--7/9/18 through 7/26/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 9-1D to MLV 17-1: Pig runs - Chemical Cleaning 2/15/18 - 2/18/18, Gauge 2/19/18, AFD 2/21/18, EMAT 2/23/18
--2/15/18 through 2/23/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 10-1 to MLV 12-1: Pressure Weld Replacement
--5/1/18 through 6/15/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 11A: New Station Tie-In (100-1 line)
"Sta 11A: New Station Tie-In (100-2 line)
--6/18/18 through 6/25/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 17-1S to MLV 20-1: Pig runs - Cleaning 5/2/18, Gauge 5/3/18, MFL 5/10/18, Hard Spot 5/15/18
--5/2/18 through 5/15/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 17-2S to MLV 20-2: Pig runs - Cleaning 6/12/18, Gauge 6/13/18, Geometry 6/19/18, MFL 6/21/18
--6/12/18 through 6/21/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 17-3D to MLV 20-3: Pig runs - Cleaning 5/22/18, Gauge 5/23/18, MFL 5/31/18
--5/22/18 through 5/31/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 25-3D to MLV 27-3: Remediation
--3/13/18 through 4/16/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
400448 – CICO/TGP MERCY GU 1 LIBERTY
"MLV 27-3A to 28-3: Remediation
--4/17/18 through 4/21/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 28-3 to 30-3: Remediation
--4/24/18 through 5/5/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
412738 – TECOGATH/TGP TECO INDIAN SPRINGS PO
"MLV 32-2D to MLV 39-2: Pig runs - Cleaning / Gauge 4/3/18 & 4/4/18, Combo 4/5/18, Hard Spot Smart Tool 4/10/18
--4/3/18 through 4/10/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 32-1 to MLV 34-1: Spike Test
--6/4/18 through 7/27/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLVS 36-1: Pipe Replacement and Install New Valve
--1/7/19 through 3/1/19: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
"MLVS 36-2: Pipe Replacement and Install New Valve
--10/22/18 through 12/28/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
"MLVS 36-3: Pipe Replacement and Install New Valve
--8/13/18 through 10/19/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
"MLV 40-2 to MLV 41-2: Spike Test
--2/12/18 through 4/13/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***MLV 40-1D to MLV 47-1: Pig runs - DEF Inspection 6/12/18, TDW MDS 6/14/18
--6/12/18 through 6/14/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 7/17/18 to 7/19/18.
"MLV 40-3S to MLV 47-3: Make Piggable
--9/10/18 through 11/30/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Beer Creek Storage: Shut In Test
--4/24/18 through 5/1/18: This project will require taking the facility out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
460017 STORAGE – BEAR CREEK
"MLV 42-2 to MLV 47-2: Pig runs - Cleaning 7/24/18, Gauge 7/26/18
--7/24/18 through 7/26/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 54-4 to MLV 63-4: Pig runs - AFD 4/24, EMAT 4/26
--9/24/18 through 10/4/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***MLV 63-1 to MLV 69-1: Pig runs - Chem Cleaning 6/4/18 to 6/16/18, AFD 6/26/18, EMAT 6/28/18
--6/4/18 through 6/28/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 2/26/18 to 3/22/18.
"MLV 63-1 to MLV 69-1: Pig runs - MFL 8/2/18, Hard Spot 8/7/18
--8/2/18 through 8/7/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 63-3 to MLV 71-3: Pig runs - Chem Cleaning 7/20/18, Gauge Plate 7/23/18, Caliper 7/24/18, MDS 7/26/18
--7/20/18 through 7/26/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 63-4D to MLV 71-4: Pig runs - AFD 3/13, EMAT 3/15
--10/6/18 through 10/25/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***MLV 71-1 to MLV 77-1: Pig runs - Chem Cleaning 3/9/18 to 3/14/18, AFD 3/20/18, EMAT 3/22/18
--3/9/18 through 3/22/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 3/9/18 to 4/5/18.
"MLV 77-1 to MLV 79-1: Pig runs - Chem Cleaning 4/9/18, AFD 4/10/18, EMAT 4/12/18
--4/9/18 through 4/12/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***MLV 78-4 to 79-4D: Pipe Replacement
--10/26/17 through 3/30/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 10/26/17 to 2/16/18.
"MLV 110-2 to MLV 114-2: Pig runs - Cleaning / Gauge 7/10/18, MFL 7/12/18, Hard Spot Tool 7/17/18
--7/10/18 through 7/17/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The meters listed below will be shut-in for a brief period of time during the pig run. Potential out of path restrictions may be at risk.
412742 BIGSANDY/TGP GLANCY CARTER
"MLV 110-6 to MLV 114-6: Pig runs - Cleaning / Gauge 7/9/18, MFL 7/19/18
--7/9/18 through 7/19/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 111-3 to MLV 114-3: Remediation
--3/20/18 through 4/9/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 111-3 to MLV 114-3: Pig runs - Cleaning & Gauge Tool 10/10/18, AFD Tool 10/16/18, EMAT 10/18/18
--10/10/18 through 10/18/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The meters listed below will be shut-in for a brief period of time during the pig run. Potential out of path restrictions may be at risk.
420762 – MPC/TGP UDP NAPLES SALES GREENUP
420045 – COL GAS/TGP MAVITY KY BOYD
"MLVS 118-3: Make Piggable
--4/30/18 through 6/2/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 114-3DL: Replace Valve
--3/6/18 through 3/12/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLVS 115-2: Drip Removal
--3/13/18 through 3/27/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 115-2A: Install Valve
"MLV 115-3: Pipe Replacement
--4/16/18 through 4/30/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 118-1 to MLV 121-1: Pig runs - Cleaning / Gauge 5/1/18, MFL 5/2/18
--5/1/18 through 5/2/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
200 Line Outages
"***MLV 200-1D to MLV 200-1A: Drip Removal
--5/30/18 through 6/6/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Added
"***Sta 200: Unit 10A: Unit Maintenance
--2/26/18 through 3/2/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 200: Unit 11A: Unit Maintenance
--2/19/18 through 2/23/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 200-2D to MLV 204-2: Pig runs - Cleaning / Gauge 6/19/18, MFL 6/21/18
--6/19/18 through 6/21/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 200-3A to MLV 200-3: Pig runs - Cleaning / Gauge 5/15/18, MFL 5/17/18, Hard Spot Tool 5/22/18
--5/15/18 through 5/22/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"***Sta 204: Unit 2A: Unit Maintenance
"***MLV 204-2D to MLV 205-2: Drip Removal
--5/16/18 through 5/23/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 204: Unit 4A: Unit Maintenance
--2/26/18 through 3/9/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLV 204-4BL to MLV 205-4: Drip Removal
"MLV 204-4 to MLV 209-4: Pig runs - Cleaning / Gauge 8/14/18, MFL 8/16/18
--8/14/18 through 8/16/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 209-1 to MLV 214-1: Pig runs - Cleaning / Gauge 7/10/18, MFL 7/12/18, Hard spot 7/17/18
--7/10/18 through 7/17/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta 209: Unit 11A: Unit Maintenance
--2/21/18 through 2/23/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 209-3 to MLV 214-3: Pig runs - Cleaning / Gauge 7/24/18, MFL 7/26/18, Hard spot 7/31/18
--7/24/18 through 7/31/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta 209: Unit 7A: Turbocharger replacement
"***Sta 214: Annual ESD test
--5/7/18 through 5/14/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 214-1A: Foundation Replacement
--3/27/17 through 2/28/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 217A-201.3 to MLV 217A-202.3: Pig runs - Cleaning / Gauge 6/5/18, MFL 6/8/18
--6/5/18 through 6/8/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 219-2D to MLV 307-1: Pig runs - Cleaning / Gauge 5/15/18, MFL 5/18/18
--5/15/18 through 5/18/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"***Sta 219: Unit 7A: Unit Maintenance
--2/26/18 through 3/1/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta 219: Unit 8A: Unit Maintenance
--3/5/18 through 3/9/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 224-1 to MLV 229-1: Pig runs - Cleaning / Gauge 9/11/18, MFL 9/13/18
--9/11/18 through 9/13/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 230-1 to MLV 237-1: Remediation
--9/17/18 through 10/5/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 237-2 to MLV 238-2: SCCDA
--8/6/18 through 8/17/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 241: Annual ESD test
--5/21/18 through 5/25/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 241: Unit 1A: Unit Maintenance
--4/16/18 through 4/20/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 241: Unit 1B: Unit Maintenance
--4/23/18 through 5/4/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 249: Unit 2B: Unit Maintenance
"Sta 245: Unit 1C: Unit Maintenance
--5/7/18 through 5/11/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 241: Unit 2B: Unit Maintenance
--5/14/18 through 5/25/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 245: Annual ESD test
--6/11/18 through 6/15/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 245-2D to MLV 249-2: Pig runs - Cleaning / Gauge 5/8/18, Combo 5/9/18
--5/8/18 through 5/9/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta 249: Annual ESD test
--5/7/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 249: Unit 1A: Unit Maintenance
--5/7/18 through 5/18/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 249: Unit 1B: Unit Maintenance
--4/9/18 through 4/20/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 249: Unit 2A: Unit Maintenance
--5/28/18 through 6/8/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 252-1 to MLV 252-1: Pressure Test
--6/4/18 through 7/6/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 254: Annual ESD test
--5/15/18 through 5/27/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 254: Station Automation and Maintenance
"***MLV 254-2 to MLV 261-2: Pig runs - Cleaning / Gauge 5/15/18, AFD 5/16/18, Cleaning 10/23/18, EMAT 10/24/18
--5/15/18 through 10/24/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled 5/14/18 to 5/17/18.
"Sta 254: Building A: Automation Upgrade - 2 weeks/unit - up to 2 units may be down at a same time
--5/28/18 through 7/28/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 254: Unit 2A: Unit Maintenance
--3/5/18 through 6/30/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 254: Unit 2B: Unit Maintenance
--5/21/18 through 5/25/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 261-2 to MLV 267-2: Remediation
--5/14/18 through 5/25/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 261BP-101-BERKSHIRE POWER DELIVERY: 1000 - 0+00 to MLV 261BP-101-BERKSHIRE POWER DELIVERY: ECDA
--6/18/18 through 6/25/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 265E-201 to MLV 265E-202: Pressure Test
--7/23/18 through 8/18/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
420758 – NARNGST/TGP LINCOLN SMS PROVIDENCE
"Sta 265E: 4000 hr Inspection
--5/5/18 through 5/18/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"265E: 4000 hr Inspection
--11/5/18 through 11/15/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 266A: Building A: Controls
--3/19/18 through 3/23/18: This project will require a building outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 266A: Annual ESD test
--10/1/18 through 10/5/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 266A-101R to MLV 266A-101L: Pig runs - Cleaning / Gauge 4/17/18, Combo 4/18/18
--4/17/18 through 4/18/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 266C-101.1 to MLV 266C-102: Pig runs - Cleaning / Gauge 6/19/18, Combo 6/20/18
--6/19/18 through 6/20/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 266A-102A to 266A-103R: Pig runs - Cleaning / Gauge 4/23/18, Combo 4/24/18
--4/23/18 through 4/24/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta 266A: Unit 1B: 4000 hr Inspection
--6/11/18 through 6/15/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"267-1: Class Change
--7/1/18 through 8/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 267: Annual ESD test
--8/21/18 through 8/22/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 267-1 to MLV 270C-101.1: Pig runs - Cleaning / Gauge 5/29/18, Combo 5/30/18, Hard Spot Tool 6/4/18
--5/29/18 through 6/4/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 267-2 to MLV 273-2: Pig runs - Cleaning / Gauge 4/11/18, Combo 4/12/18
--4/11/18 through 4/12/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 268A-301 to MLV 268A-302: Pressure Test
--7/2/18 through 7/21/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
420111 – BOSTN/TGP LEOMINSTER MA WORCHESTER
"MLV 270C-101 to MLV 270C-102: Remediation
--5/7/18 through 5/16/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 270C-501 to MLV 270C-502: Remediation
--5/18/18 through 5/26/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 270B: Annual ESD test
--10/23/18 through 10/25/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 270B-101.1 to MLV 270B-102: Pig runs - Cleaning / Gauge 6/6/18, Combo 6/7/18, Hard Spot Tool 6/12/18
--6/6/18 through 6/12/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 270B-103 to MLV 270B-104: Pig runs - Cleaning / Gauge 5/22/18, Combo 5/23/18
--5/22/18 through 5/23/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 270B-104 to MLV 270B-105: Pig runs - Cleaning / Gauge 4/26/18, Combo 4/27/18
--4/26/18 through 4/27/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 270B-105 to MLV 270B-105: Pig runs - Cleaning / Gauge 5/2/18, Combo 5/3/18
--5/2/18 through 5/3/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 273B-101 to MLV 273B-102: Remediation
--5/29/18 through 6/1/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 273C-101 to MLV 273C-103: Remediation
--6/4/18 through 6/16/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
300 Line Outages
"Sta 303A: Unit 1A: Unit Maintenance
--4/2/18 through 4/13/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta 307: Unit 5A: Unit Maintenance
"MLV 313-1 to MLV 317-1: Remediation
--7/23/18 through 8/10/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Ellisburg Storage: Shut-In Test
--4/16/18 through 4/23/18: This project will require taking the facility out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
460012 – DOMINION/TGP ELLISBURG INJECTION PO
"Harrison Storage: Shut-In Test
--3/19/18 through 3/26/18: This project will require taking the facility out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
460004 – DOMINION/TGP HARRISON INJECTION POT
"Hebron Storage: Shut In Test
400485 HEBRON STORAGE INJECTION POTTER
470001 HEBRON STORAGE WITHDRAWAL POTTER
"MLV 315-2 to MLV 317-2: Remediation
--8/13/18 through 8/17/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta 315: Unit 2A: Repair Exhaust Leak
--2/26/18 through 2/28/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 317-1BL to MLV 319-1: Remediation
--6/4/18 through 6/8/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 317: Unit 1B: Compressor Maintenance
--6/1/18 through 6/30/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta 317: Unit 1B: Electric Company Outage
--4/20/18 through 4/23/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
--5/18/18 through 5/21/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 319-1 to MLV 321-1: Remediation
--5/21/18 through 6/1/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 319-2 to MLV 321-2: Pig runs - Cleaning / Gauge 4/24/18, MFL 4/26/18
--4/24/18 through 4/26/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLVS 319: Meter Tie-In
--5/20/18 through 5/25/18: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 321-1 to MLV 325-1: Remediation
--6/18/18 through 7/20/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
400 Line Outages
"MLV 400-1 (STATION 1) to MLV 409-1: Remediation
--2/27/18 through 3/16/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLV 400-2 (STATION 1) to MLV 409-2: Remediation
--3/19/18 through 3/30/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled 4/19/18 to 4/30/18.
"MLV 409A-101 TO MLV 409A-103: Remediation
--4/2/18 through 4/9/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta 409: Unit 1A: Unit Maintenance
--3/12/18 through 4/16/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 409A-901 to MLV 409A-902: Pig runs - Maintenance 4/13/18, Gauge 4/14/18, MFL 4/20/18
--4/13/18 through 4/20/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
500 Line Outages
"MLV 538-1 to MLV 542-1: Remediation
--3/12/18 through 3/17/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 542: Station Maintenance
--9/10/18 through 9/14/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 546: Unit 1A: Unit Maintenance
--4/16/18 through 4/27/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 546: Unit 2A: Unit Maintenance
--4/30/18 through 5/11/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta 546: Unit 4A: Unit Maintenance
--5/14/18 through 5/25/18: This project will require a unit outage, which could limit throughput through the station and result in restrictionThis project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.s based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 549-3 to MLV 550-3: ILI Only
--8/7/18 through 8/8/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta. 550-1A: Unit Maintenance
--8/15/17 through 6/1/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta 555: Annual ESD test
--5/14/18 through 5/20/18: This project will require the station outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***MLV 559-2 to MLV 565-2: Pig runs - Cleaning 3/26/18, MFL 3/28/18
--3/26/18 through 3/28/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled 2/19/18 to 2/21/18.
"MLV 561-1 to MLV 563-1: Pressure Test
--6/11/18 through 7/13/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 561-1 to MLV 563-1: Tethered ILI
"MLV 561-1 to MLV 563-1: ECDA
"Sta 563: Tie-In to 500-1, 500-2, & 800-1
--3/13/18 through 4/9/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
700 Line Outages
"MLV 700-1 to MLV 706-1: Pig runs - Cleaning / Gauge 9/17/18 - 9/19/18, Combo 9/20/18, Hard Spot Tool 9/24/18
--9/17/18 through 9/24/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
800 Line Outages
"Sta 823: Purchase Power Conversion
--8/27/18 through 8/30/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers in the area may experience higher than normal pressure for the duration of the outage. Potential out of path restrictions may be at risk.
"MLV 824-1 to 825-1: Pipe Recoat
--3/7/18 through 4/13/18: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 834-1 to MLV 835-1: Spike Test
--4/17/18 through 5/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
412691 REGENCY/TGP PEOPLES ROAD FRANKLIN
49554 – AM MIDLA/TGP NORTH PEOPLES RD FRANK
420279- ATMOS TL/TGP CROWVILLE LA FRANKLIN
"MLV 834-1 to MLV 838-1: Remediation
--5/7/18 through 5/10/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***MLV 843-1: Trap Modification
--3/7/18 through 3/8/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 3/5/18 to 3/6/18.
"MLV 843-1 to MLV 847-1: Pig runs - Cleaning 6/18/18, Gauge Plate 6/19/18, MFL 6/20/18, Hard Spot 6/26/18
--6/18/18 through 6/26/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 846-1 to MLV 847-1: Hydrotest
--4/17/18 through 5/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
420328 – ATMOS-MS/TGP HARDY STA MS GRENADA
"***Sta. 847: Station Reversal
--8/12/17 through 3/16/18: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 8/12/17 to 2/24/18.
"MLV 851-1 to MLV 851-1: Spike Test
--7/18/18 through 9/28/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 856-1 to MLV 859-1: Pig runs - Cleaning 7/10/18, Gauge 7/11/18, MFL 7/12/18, Hard Spot 7/17/18
--7/10/18 through 7/17/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 866-1D to MLV 871-1: Remediation
--7/9/18 through 7/20/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 871-1 to MLV 876-1: Remediation
--7/23/18 through 8/31/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
If you have any questions, please contact your Scheduler.