Effective Timely Cycle (9:00) for the gas day of January 18, 2018 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO Daily Critical Day 1 System Wide for under-deliveries into the system and over-takes out of the system for all balancing parties
OFO Daily Balancing Alert Meter Specific 420926 for over-takes out of the system
OFO Daily Balancing Alert Meter Specific 412829 for under-deliveries into the system
RESTRICTIONS
STA 9 (Segment 109 BH) – through 100% of SIPsp due to scheduled maintenance; 55,186 Dths
Heidelberg Delivery Meter (Pin 420291) – through approx 18% of SOP due to nominations in excess of operational capacity; 2,117 Dths
Dominion Broad Run Cornwell (Pin 420044) – through 100% of SOP receipts due to emergent repair; 100,000 Dths
STA 204 (Segment 204 BH) – through 100% of IT due to scheduled maintenance; 9 Dths
Carroll County Home Delivery Meter (Pin 49198) – through approx 39% of IT due to nominations in excess of operational capacity; 4,417 Dths
STA 224 (Segment 224 FH) / HC Zn 5 (Segment 299 FH) – through 100% of SOP due to nominations in excess of operational capacity; 990,443 Dths
STA 245 (Segment 245 FH) – through 100% of SOP due to nominations in excess of operational capacity; 551,428 Dths
Wright Receipt Meter (Pin 412181) – through approx 86% of SOP due to nominations in excess of operational capacity; 397,399 Dths
STA 254 (Segment 256 FH) – through 100% of SOP due to nominations in excess of operational capacity; 88,346 Dths
STA 261 Discharge (Segment 261 FH) – through 100% of SOP due to nominations in excess of operational capacity; 192,996 Dths
STA 267 (Segment 266 FH) - through 100% of SOP due to nominations in excess of operational capacity; 92,455 Dths
Fitchburg to Gloucester (Segment 268 FH) - through 100% of SOP due to nominations in excess of operational capacity; 25,639 Dths
Mendon Delivery Meter (Pin 420285) – through 100% of SOP receipts due to displacement gas unavailable for backhaul; 4,990 Dths
MLV 273 (Segment 284 FH) – through approx 80% of SOP due to nominations in excess of operational capacity; 102,476 Dths
STA 307 (Segment 307 BH) – through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 10,000 Dths
STA 315 (Segment 315 BH) – through 100% of SOP due to scheduled maintenance; 20,000 Dths
STA 321 (Segment 321 FH) - through 100% of SOP due to nominations in excess of operational capacity; 623,033 Dths
STA 325 (Segment 324 FH) - through approx 82% of SOP due to nominations in excess of operational capacity; 208,375 Dths
Rivervale Delivery Meter (Pin 420101) – through approx 32% of SIPps due to nominations in excess of operational capacity; 37,256 Dths
MLV 336 (Segment 336 FH) – through approx 65% of SOP due to nominations in excess of operational capacity; 896 Dths
LINEPACK RESTRICTIONS
No payback FROM the pipe System Wide
No Park Withdrawals or Loans under Rate Schedule PAL for PAL-D or PAL-AO Services System Wide
STORAGE RESTRICTIONS
No Authorized Overrun Storage Withdrawals from Northern Storage (460018), Portland Storage MA (460025), Portland Storage PA (460020) or Bear Creek Storage (460017) (FSMA-AO, FSPA-AO)
No Interruptible Service Storage Withdrawals from Northern Storage (460018), Portland Storage MA (460025), Portland Storage PA (460020) or Bear Creek Storage (460017) (IS-MA, IS-PA)
No transfers from FS storage accounts to IS storage accounts at Northern or Bear Creek Storage Fields
No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (IS-PA, FS-PA)
Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR
CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND
ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED
SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.