Subject:  Updated TGP Scheduled Outages
Notice Text:

November 7, 2017

 

TO:  ALL TENNESSEE CUSTOMERS

 

RE:  UPDATED TGP SCHEDULED OUTAGES

 

This notice is an update of the 2017 planned outages and maintenance

activities on Tennessee Gas Pipeline.

 

The Outage and Maintenance schedule is available in an Excel

spreadsheet format which may be found in DART.

 

Some projects may reduce capacity to a level below anticipated

demand (nominations), or require taking individual meters out of

service. 

 

For each project, based upon anticipated demand, the highest

level of service Tennessee expects to be impacted is noted. 

Unless noted otherwise, all impacts are in the Supply to Market

direction.

 

Projects may be added, altered, delayed or canceled.  Tennessee

will provide updates by posting revisions on a weekly basis or

more often if necessary.

 

Projects revised or added since the last posting are preceded

by ***.  Within the Excel Spreadsheet and Adobe Files, revisions

are highlighted and an asterisk has been added to the "Revised"

column.

 

Unless otherwise noted, all listed meters will be physically shut

-in for the duration of the project.

 

Unless otherwise noted, all scheduled dates represent gas days

as defined in the Tennessee Gas Pipeline tariff to mean a period

of twenty-four consecutive hours, beginning and ending at 9:00

a.m. (Central Clock Time).

 

=========================

Completed Outages

=========================

"***Meter 421017:  Meter Tube Cleaning

***Completed

The following meters are available for nominations:

421017 - GDR/TGP RIO BRAVO HIDALGO

………………………………"

=========================

100 Line Outages

=========================

"MLV 1-1D to MLV 9-1S:  Remediation

--1/15/18 through 3/10/18:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project.  Potential in the path restrictions may be at risk.

………………………………"

"MLV.9-1S to MLV.1-1D:  EMAT

--1/16/18:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"***MLV.9-1S to MLV.1-1D:  ILI/Cleaning: 11/28, 11/30, 12/19

--11/28/17 through 12/19/17:  This activity will require operating at controlled flow rates. The meters listed below will be temporary shut-in while the pig passes.  Potential in the path restrictions may be at risk.

412490  UES/TGP RENEWAL CENTER DEHY VICTORI

421083 DEVON GS/TGP PORT OF VICTORIA: DIP

410063 GCENGY/TGP UDP ROCHE DEHY REFUGIO

412877 EF MIDS/TGP BANQUETE PLANT: RIP 1T

***Date Change, Previously scheduled 11/28/17 to 12/5/17.

………………………………"

"***MLV 9-1S to MLV 1-1D:  Chemical Clean Tool Run

--12/12/17 through 12/14/17:  This activity will require operating at controlled flow rates. The meters listed below will be temporary shut-in while the pig passes.  Potential in the path restrictions may be at risk.

412490  UES/TGP RENEWAL CENTER DEHY VICTORI

421083 DEVON GS/TGP PORT OF VICTORIA: DIP

410063 GCENGY/TGP UDP ROCHE DEHY REFUGIO

412877 EF MIDS/TGP BANQUETE PLANT: RIP 1T

***Added

………………………………"

"Sta. 17:  Station Reversal

--5/31/16 through 12/15/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 17-1 to 12-1:  Pressure Weld Replacement

--9/15/17 through 12/15/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project.  Potential in the path restrictions may be at risk.

400454 H-M RES/TGP UDP Egypt North West Dehy

420162 Cokinos/TGP Raun Farm #2

420479 Cokinos/TGP Cattle Farm (Garwood PD)

412023 HGI/TGP Englehardt (Garwood Plate) Colorado

420332 Cokinos/TGP Nitsch Farm

421054 Cokinos/TGP Swanson Farm

420467 Cokinos/TGP Holob Farm

420466 Cokinos/TGP Holt Farm

420442 Cokinos/TGP Rasmussen Farm (Abeulo)

412723 Patterson/TGP Hill

412523 UES/TGP Wildcat Rasmussen #1

420369 Cokinos/TGP Wiggington Farm

420183 Cokinos/TGP Krenek Farm

420158 Cokinos/TGP Raun Farm #1

420185 Cokinos/TGP Ottis Farm

………………………………"

"Sta. 32:  Cooling Water and Oil System Modification

--10/2/17 through 12/15/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV.39-1 to MLV.40-1:  Wrinkle Bend Remediation

--11/28/17 through 12/15/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 78-2 to 79-2:  Pipe Replacement

--10/26/17 through 12/15/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 78-4 to 79-4D:  Pipe Replacement

--10/26/17 through 12/31/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta.106:  Tie Ins

--12/11/17 through 12/15/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience pressure and flow fluctuations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 118-1:  Broad Run Expansion Tie-In

--12/1/17 through 12/12/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  The meters listed below will be shut-in for the entire duration of the project.  Potential in the path restrictions may be at risk.

420639 – DOMINION/TGP INSTITUTE SALES KANAWH

420409 – CRANBERY/TGP INSTITUTE WV KANAWHA

………………………………"

"MLV 119-2:  Broad Run Expansion Tie-In

--12/13/17 through 12/19/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project.  Potential in the path restrictions may be at risk.

420749 – CRANBERY/TGP CRANBERRY SALES KANAWH

………………………………"

=========================

200 Line Outages

=========================

"Sta. 204-8A:  Unit Maintenance

--10/16/17 through 12/31/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 214-1A:  Foundation Replacement

--3/27/17 through 2/28/18:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"***Sta. 214-10A:  Unit Valve Replacement

--10/30/17 through 12/8/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Date Change, Previously scheduled 10/30/17 to 11/30/17.

………………………………"

"Sta. 214-12A:  Unit Maintenance

--12/1/17 through 12/31/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

=========================

300 Line Outages

=========================

"Sta. 307-4A:  Unit Maintenance

--5/15/17 through 12/15/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 315:  Protective Device Test

--12/19/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"***Meter 420203:  Meter Station Upgrade

--6/23/17 through 12/18/17:  This project will require a meter station outage. The listed meter below will be shut-in for the entire duration of the project.  Potential in the path restrictions may be at risk.

420203 - UGIPENN/TGP UNIONDALE PA SUSQUEHANNA

***Date Change, Previously scheduled 6/23/17 to 12/1/17.

………………………………"

 

=========================

500 Line Outages

=========================

"***Sta. 500C1:  Controls Upgrade

--10/30/17 through 12/7/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Date Change, Previously scheduled 10/30/17 to 11/30/17.

………………………………"

"Sta. 550-1A:  Unit Maintenance

--8/15/17 through 12/9/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"***MLV 561-1 to MLV 563-1:  Pressure Test

--6/11/18 through 7/13/18:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

420788 – DICKSON/TGP KINGSTON SPRINGS SALES

420312 – PIEDMNT/TGP NASHVILLE TN 2 ROBERTS

***Date Change, Previously scheduled 5/7/18 to 6/22/18.

………………………………"

"***MLV 561-1 to MLV 563-1:  Pressure Test

--6/11/18 through 7/13/18:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

420788 – DICKSON/TGP KINGSTON SPRINGS SALES

420312 – PIEDMNT/TGP NASHVILLE TN 2 ROBERTS

***Added

………………………………"

"***MLV 561-1 to MLV 563-1:  Tethered ILI

--6/11/18 through 7/13/18:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

420788 – DICKSON/TGP KINGSTON SPRINGS SALES

420312 – PIEDMNT/TGP NASHVILLE TN 2 ROBERTS

***Date Change, Previously scheduled 12/31/18.

………………………………"

"***MLV 561-1 to MLV 563-1:  Tethered ILI

--6/11/18 through 7/13/18:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

420788 – DICKSON/TGP KINGSTON SPRINGS SALES

420312 – PIEDMNT/TGP NASHVILLE TN 2 ROBERTS

***Added

………………………………"

"***MLV 561-1 to MLV 563-1:  ECDA

--6/11/18 through 7/13/18:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

420788 – DICKSON/TGP KINGSTON SPRINGS SALES

420312 – PIEDMNT/TGP NASHVILLE TN 2 ROBERTS

***Date Change, Previously scheduled 12/31/18.

………………………………"

"***MLV 561-1 to MLV 563-1:  ECDA

--6/11/18 through 7/13/18:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

420788 – DICKSON/TGP KINGSTON SPRINGS SALES

420312 – PIEDMNT/TGP NASHVILLE TN 2 ROBERTS

***Added

………………………………"

"Sta. 823:  Cooling System Upgrade

--10/1/17 through 12/15/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers in the area may experience higher than normal pressure for the duration of the outage.  Potential out of path restrictions may be at risk.

………………………………"

=========================

800 Line Outages

=========================

"Sta. 827:  Station Reversal

--5/9/17 through 12/31/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 827-1 to 829-1A:  Pipe Replacement

--12/5/17 through 12/14/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 834-1 to MLV 835-1:  Spike Test

--2/5/18 through 3/17/18:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project.  Potential out of path restrictions may be at risk.

412691 REGENCY/TGP PEOPLES ROAD FRANKLIN

49554 – AM MIDLA/TGP NORTH PEOPLES RD FRANK

420279- ATMOS TL/TGP CROWVILLE LA FRANKLIN

………………………………"

"Sta. 847:  Station Reversal

--8/12/17 through 12/14/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"***MLV 872-2 to MLV 873-2A:  Anomaly Remediation

--11/27/17 through 12/9/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and will result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

***Date Change, Previously scheduled 11/27/17 to 12/3/17.

………………………………"

 

If you have any questions, please contact your Scheduler.

 

..